360-362 1/2 E 62ND ST 90003

Certificate Information: 360-362 1/2 E 62ND ST 90003

Application / Permit
24016-20000-30916
Plan Check / Job No.
B24VN17927
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/29/2025
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2024 APPLICANT
Assigned to Plan Check Engineer 10/2/2024 SERGIO MUNIZ
Corrections Issued 10/3/2024 SERGIO MUNIZ
Plan Check Approved 3/5/2025 PINANK PATEL
Issued 5/29/2025 APPLICANT
CofO in Progress 2/12/2026 ALEJANDRO DE ARTOLA
No Progress 2/13/2026 MICHAEL LEWIS
CofO in Progress 2/13/2026 MICHAEL LEWIS
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/17/2024 CELINA MORENO
Sewer availability Cleared 10/17/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/25/2024 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/3/2025 Approved ENRIQUE MIRELES
Pre-Inspection 8/12/2025 Partial Inspection SABAS ALONSO
Pre-Inspection 9/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/4/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 11/4/2025 Approved BARRY HACHE
ELECTRICAL-Rough 11/19/2025 Approved SABAS ALONSO
Green Building Rough 11/19/2025 Approved SABAS ALONSO
HVAC-Rough 11/19/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 11/21/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 11/21/2025 Approved ALEJANDRO DE ARTOLA
Insulation 11/21/2025 Approved ALEJANDRO DE ARTOLA
Final 12/16/2025 Corrections Issued LUIS CASTRO
Green Building Final 12/16/2025 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 12/16/2025 Approved LUIS CASTRO
Final 1/13/2026 Corrections Issued LUIS CASTRO
Green Building Final 1/13/2026 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 2/2/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/2/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 2/2/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 2/2/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 2/2/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/11/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/12/2026 Approved ALEJANDRO DE ARTOLA
Final 2/12/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
PLUMBING-Final 2/12/2026 Approved ALEJANDRO DE ARTOLA