15923-15925 W LEMARSH ST 91343

Certificate Information: 15923-15925 W LEMARSH ST 91343

Application / Permit
24016-20000-30861
Plan Check / Job No.
B24VN17876
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. CONVERT EXISTING GARAGE AND BREEZEWAY TO NEW JADU (484 SF) PER GCS 65852.2(e)(1)(A) and 65852.22.
Permit Issued
Issued on 12/24/2024
Issuing Office
Current Status
CofO Issued on 6/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2024 APPLICANT
Assigned to Plan Check Engineer 10/2/2024 TSE MING HUANG
Corrections Issued 10/2/2024 TSE MING HUANG
Applicant returned to address corrections 10/30/2024 TSE MING HUANG
Applicant returned to address corrections 11/27/2024 TSE MING HUANG
Applicant returned to address corrections 12/4/2024 TSE MING HUANG
Plan Check Approved 12/24/2024 ADAM HEGAZI
Issued 12/24/2024 APPLICANT
CofO in Progress 6/23/2025 CHRISTOPHER ROJAS
Permit Finaled 6/27/2025 RUBEN SALAS
CofO Issued 6/27/2025 RUBEN SALAS
Permit Finaled 6/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/7/2024 RYAN CASTRO
Sewer availability Cleared 10/7/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/8/2024 RYAN CASTRO
Grading Pre-Inspection Cleared 10/9/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/3/2025 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 1/14/2025 Corrections Issued JAVIER RAMOS JR
Sewer 1/14/2025 Approved JAVIER RAMOS JR
Underground Mechanical 1/14/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 2/7/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/7/2025 Approved JAVIER RAMOS JR
HVAC-Rough 2/7/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/7/2025 Approved JAVIER RAMOS JR
Wood Frame 2/7/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Not Ready for Inspection JAVIER RAMOS JR
Insulation 2/21/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 2/21/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 2/21/2025 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 3/4/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Approved JAVIER RAMOS JR
Green Building Rough 3/4/2025 Approved JAVIER RAMOS JR
Insulation 3/4/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/4/2025 Approved JAVIER RAMOS JR
Shower Pan 3/4/2025 Approved JAVIER RAMOS JR
Drywall Nailing 3/10/2025 Approved JAVIER RAMOS JR
Pre-Inspection 3/28/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 6/3/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 6/3/2025 Corrections Issued CHRISTOPHER ROJAS
Gas Test 6/3/2025 Approved CHRISTOPHER ROJAS
Green Building Final 6/3/2025 OK to Expire Permit CHRISTOPHER ROJAS
HVAC-Final 6/3/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 6/3/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Approved CHRISTOPHER ROJAS
Sewer 6/3/2025 Approved CHRISTOPHER ROJAS
Smoke Detectors 6/3/2025 Approved CHRISTOPHER ROJAS
Final 6/17/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Final 6/17/2025 Approved CHRISTOPHER ROJAS
Final 6/23/2025 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 6/23/2025 Approved CHRISTOPHER ROJAS