11052 N RUFFNER AVE 91344
Certificate Information: 11052 N RUFFNER AVE 91344
- Application / Permit
- 24016-20000-30783
- Plan Check / Job No.
- B24VN17806
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERSION OF (E) DETACHED GARAGE TO A 412 SF ADUper CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2024 | YASHAR EMAMI |
| Corrections Issued | 10/7/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 11/13/2024 | YASHAR EMAMI |
| Plan Check Approved | 12/9/2024 | ALFREDO JARA |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 7/2/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/19/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/19/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zargari,, Ramin; Lic. No.: S4119 | 5743 CORSA AVE STE 204 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/10/2025 | Partial Approval | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 2/12/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/12/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/24/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/24/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/7/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 3/7/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/7/2025 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 3/7/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 3/26/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 4/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 4/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/19/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/19/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 6/3/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Final | 6/23/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 7/2/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 7/2/2025 | Approved | CHRISTOPHER ROJAS |