11052 N RUFFNER AVE 91344

Certificate Information: 11052 N RUFFNER AVE 91344

Application / Permit
24016-20000-30783
Plan Check / Job No.
B24VN17806
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. CONVERSION OF (E) DETACHED GARAGE TO A 412 SF ADUper CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/17/2025
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2024 APPLICANT
Assigned to Plan Check Engineer 10/7/2024 YASHAR EMAMI
Corrections Issued 10/7/2024 YASHAR EMAMI
Applicant returned to address corrections 11/13/2024 YASHAR EMAMI
Plan Check Approved 12/9/2024 ALFREDO JARA
Issued 1/17/2025 APPLICANT
CofO in Progress 7/2/2025 CHRISTOPHER ROJAS
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/19/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 10/19/2024 CARLOS AGUILERA
Sewer availability Cleared 10/19/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/22/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zargari,, Ramin; Lic. No.: S4119 5743 CORSA AVE STE 204      WESTLAKE VILLAGE, CA 91362

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/10/2025 Partial Approval DAVID ANDERSON
Deputy Drilled-In Anchors 2/12/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/12/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/24/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 2/24/2025 Approved JAVIER RAMOS JR
HVAC-Rough 2/24/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/24/2025 Approved JAVIER RAMOS JR
HVAC-Rough 3/7/2025 Approved JAVIER RAMOS JR
Insulation 3/7/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 3/7/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 3/7/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/26/2025 Approved CHRISTOPHER ROJAS
Insulation 3/26/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 4/3/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 4/3/2025 Approved NICHOLAS TROWBRIDGE
Final 5/19/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/19/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 5/19/2025 Approved CHRISTOPHER ROJAS
Final 6/3/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Approved CHRISTOPHER ROJAS
Final 6/23/2025 Partial Approval CHRISTOPHER ROJAS
Final 7/2/2025 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 7/2/2025 Approved CHRISTOPHER ROJAS