13641 W ERWIN ST 91401

Certificate Information: 13641 W ERWIN ST 91401

Application / Permit
24016-20000-30700
Plan Check / Job No.
B24VN17711
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF EXISTING SINGLE FAMILY DWELLING TO CONVERT THE EXISTING LAUNDRY INTO A NEW BATHROOM, REMOVE NON-BEARING WALL BETWEEN LIVING ROOM AND KITCHEN, SPLIT BEDROOM INTO TWO BEDROOMS AND RENOVATE KITCHEN. WORK DONE PER WFPP.
Permit Issued
Issued on 1/22/2025
Issuing Office
Current Status
Issued on 1/22/2025

Permit Application Status History

Submitted 9/27/2024 APPLICANT
Assigned to Plan Check Engineer 9/27/2024 MADISON ODELL
Corrections Issued 9/27/2024 MADISON ODELL
Applicant returned to address corrections 10/29/2024 MADISON ODELL
Applicant returned to address corrections 12/6/2024 OMAR GARNICA
Applicant returned to address corrections 1/1/2025 MADISON ODELL
Plan Check Approved 1/14/2025 MADISON O'DELL
Issued 1/22/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/2/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/9/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/24/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/29/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/3/2025 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 2/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 2/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 2/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 No Access for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/20/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 5/20/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 5/20/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 5/20/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 5/23/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 5/23/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 6/23/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 7/1/2025 Approved OGANES TARAKHCHYAN
Shower Pan 7/16/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Shower Pan 7/21/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/30/2025 Approved MICHAEL CORTEZ