6502 N COLBATH AVE 91401

Certificate Information: 6502 N COLBATH AVE 91401

Application / Permit
24016-20000-30691
Plan Check / Job No.
B24VN17701
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EXISTING SINGLE FAMILY DWELLING TO CREATE A NEW BATHROOM AND RENOVATE THE BATHROOMS AND BEDROOMS AND NEW ADDITION TO SINGLE FAMILY DWELLING. WORK DONE PER ARCHITECT DESIGN. 1 of 2
Permit Issued
Issued on 9/3/2025
Issuing Office
Metro
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 MIROOSH KHACHATOORIAN
Corrections Issued 10/3/2024 MIROOSH KHACHATOORIAN
Building Plans Picked Up 10/22/2024 APPLICANT
Plan Check Approved 2/3/2025 MADISON O'DELL
No Progress 8/11/2025 MADISON O'DELL
No Progress 8/11/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 8/22/2025 SEWADA ZADOORAN MILAGARDI
Issued 9/3/2025 APPLICANT
CofO in Progress 4/8/2026 VINCENT HANLEY
Permit Finaled 5/11/2026 RUBEN SALAS
CofO Issued 5/11/2026 RUBEN SALAS
Permit Finaled 5/11/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/20/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 8/20/2025 DERRICK MAGEE

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor Cap Angeles Construction Inc; Lic. No.: 1115382-B 757 E WILLOW STREET      ONTARIO, CA 91764

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/8/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 9/10/2025 Approved RYAN SALAZAR
Footing/Foundation/Slab 9/10/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Partial Approval RYAN SALAZAR
Insulation 9/15/2025 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 11/10/2025 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 11/10/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 11/10/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 11/10/2025 Approved JACK KARGODORIAN
Wood Frame 11/10/2025 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 11/13/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 11/13/2025 Approved RYAN SALAZAR
Green Building Rough 11/13/2025 Approved RYAN SALAZAR
HVAC-Rough 11/13/2025 Approved RYAN SALAZAR
PLUMBING-Rough 11/13/2025 Approved RYAN SALAZAR
Insulation 11/17/2025 Not Ready for Inspection CHRISTOPHER MORFIN
Interior/Exterior Lathing 11/17/2025 Not Ready for Inspection CHRISTOPHER MORFIN
Insulation 11/19/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 11/19/2025 Partial Approval MICHAEL CORTEZ
Drywall Nailing 11/21/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 11/21/2025 Partial Approval WAYNE REGESTER
Shower Pan 11/21/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 11/26/2025 Not Ready for Inspection RYAN SALAZAR
Shower Pan 11/26/2025 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 12/2/2025 Approved RYAN SALAZAR
Shower Pan 12/2/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 12/8/2025 Not Ready for Inspection RYAN SALAZAR
Service/Power Release 12/8/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 4/2/2026 Approved VINCENT HANLEY
Final 4/2/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 4/2/2026 Approved VINCENT HANLEY
PLUMBING-Final 4/2/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/2/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 4/7/2026 Approved VINCENT HANLEY
Final 4/7/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 4/7/2026 Approved VINCENT HANLEY
PLUMBING-Final 4/7/2026 Approved VINCENT HANLEY