6502 N COLBATH AVE 91401
Certificate Information: 6502 N COLBATH AVE 91401
- Application / Permit
- 24016-20000-30691
- Plan Check / Job No.
- B24VN17701
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL EXISTING SINGLE FAMILY DWELLING TO CREATE A NEW BATHROOM AND RENOVATE THE BATHROOMS AND BEDROOMS AND NEW ADDITION TO SINGLE FAMILY DWELLING. WORK DONE PER ARCHITECT DESIGN. 1 of 2
- Permit Issued
- Issued on 9/3/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 10/3/2024 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 10/22/2024 | APPLICANT |
| Plan Check Approved | 2/3/2025 | MADISON O'DELL |
| No Progress | 8/11/2025 | MADISON O'DELL |
| No Progress | 8/11/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 8/22/2025 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/3/2025 | APPLICANT |
| CofO in Progress | 4/8/2026 | VINCENT HANLEY |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
| CofO Issued | 5/11/2026 | RUBEN SALAS |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 8/20/2025 | DERRICK MAGEE |
Contact Information
| Architect | Gilliam,, Jonathan; Lic. No.: C33995 | 15017 ARCHWOOD STREET VAN NUYS, CA 91405 |
| Contractor | Cap Angeles Construction Inc; Lic. No.: 1115382-B | 757 E WILLOW STREET ONTARIO, CA 91764 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/8/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 9/10/2025 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/10/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 9/15/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/10/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/10/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 11/10/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 11/10/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 11/10/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/13/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 11/13/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 11/13/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/13/2025 | Approved | RYAN SALAZAR |
| Insulation | 11/17/2025 | Not Ready for Inspection | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 11/17/2025 | Not Ready for Inspection | CHRISTOPHER MORFIN |
| Insulation | 11/19/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 11/21/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 11/21/2025 | Partial Approval | WAYNE REGESTER |
| Shower Pan | 11/21/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 11/26/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Shower Pan | 11/26/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/2/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 12/2/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 12/8/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Service/Power Release | 12/8/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/2/2026 | Approved | VINCENT HANLEY |
| Final | 4/2/2026 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/2/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/2/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 4/2/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/7/2026 | Approved | VINCENT HANLEY |
| Final | 4/7/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 4/7/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/7/2026 | Approved | VINCENT HANLEY |