9728-9730 N SHOSHONE AVE 91325

Certificate Information: 9728-9730 N SHOSHONE AVE 91325

Application / Permit
24016-20000-30570
Plan Check / Job No.
B24VN17588
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. Convert existing 409 sq. ft. garage and 221 sq. ft. workshop to an ADU per GCS 6585.2(e)(1)(A)
Permit Issued
Issued on 2/25/2025
Issuing Office
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/30/2024 JOHN MESIAS
Corrections Issued 10/7/2024 JOHN MESIAS
Applicant returned to address corrections 12/18/2024 ALEXANDER JOO
Plan Check Approved 12/23/2024 ALEXANDER JOO
Issued 2/25/2025 APPLICANT
CofO in Progress 4/29/2026 CHRISTOPHER ROJAS
Permit Finaled 5/21/2026 RUBEN SALAS
CofO Issued 5/21/2026 RUBEN SALAS
Permit Finaled 5/21/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/9/2024 CHARLES POWELL
Address approval Cleared 10/13/2024 LEE GUILBEAUX
Sewer availability Cleared 10/13/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/13/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/16/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/25/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 4/30/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 4/30/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/23/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Pre-Inspection 6/23/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/1/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/1/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/1/2025 Approved NICHOLAS TROWBRIDGE
Deputy Wood Construction 7/2/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 7/15/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 7/15/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/18/2025 Approved NICHOLAS TROWBRIDGE
Insulation 7/30/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/30/2025 Partial Approval NICHOLAS TROWBRIDGE
Shower Pan 7/30/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 8/19/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 8/19/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 3/26/2026 Not Ready for Inspection KEVIN BERBERYAN
Final 3/26/2026 Corrections Issued KEVIN BERBERYAN
HVAC-Final 3/26/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 3/26/2026 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 3/26/2026 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 4/8/2026 Approved KEVIN BERBERYAN
Final 4/8/2026 Corrections Issued KEVIN BERBERYAN
HVAC-Final 4/8/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 4/8/2026 Approved KEVIN BERBERYAN
Smoke Detectors 4/8/2026 Approved KEVIN BERBERYAN
Special/Order Compliance 4/16/2026 Approved KEVIN BERBERYAN
Final 4/29/2026 OK to Issue CofO CHRISTOPHER ROJAS