4249 S 11TH AVE 90008

Certificate Information: 4249 S 11TH AVE 90008

Application / Permit
24016-20000-30517
Plan Check / Job No.
B24VN17547
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING PER LAMC CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/16/2025
Issuing Office
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2024 APPLICANT
Assigned to Plan Check Engineer 9/30/2024 ARTIN ZARUKIAN
Corrections Issued 10/1/2024 ARTIN ZARUKIAN
Building Plans Picked Up 10/3/2024 APPLICANT
Plan Check Approved 1/16/2025 ANGELICA MARTINEZ
Issued 1/16/2025 APPLICANT
CofO in Progress 9/15/2025 LUIS CASTRO
Permit Finaled 9/16/2025 DEROLD HAUFF
CofO Issued 9/16/2025 DEROLD HAUFF
Permit Finaled 9/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 12/31/2024 RIDWAN HARDY
Address approval Cleared 1/3/2025 DAVID VO
Eng Process Fee Ord 176,300 Cleared 1/3/2025 DAVID VO
Sewer availability Cleared 1/3/2025 DAVID VO

Contact Information

Contractor Built To Perfection Inc; Lic. No.: 837987-B 22222 SHERMAN WAY #202      CANOGA PARK, CA 91303
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/7/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 3/13/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Partial Approval LUIS CASTRO
Special/Order Compliance 3/27/2025 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 4/18/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 4/18/2025 Corrections Issued LUIS CASTRO
Green Building Rough 4/18/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 4/18/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 4/18/2025 Corrections Issued LUIS CASTRO
Special/Order Compliance 4/23/2025 Partial Inspection LUIS CASTRO
ELECTRICAL-Rough 5/5/2025 Approved LUIS CASTRO
HVAC-Rough 5/5/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 5/5/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 5/5/2025 Approved LUIS CASTRO
Shower Pan 5/8/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 5/14/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Approved LUIS CASTRO
Green Building Rough 5/14/2025 Approved LUIS CASTRO
Insulation 5/14/2025 Partial Approval LUIS CASTRO
Insulation 5/19/2025 Approved ALEX COLIN
Drywall Nailing 5/30/2025 Approved LUIS CASTRO
Sewer 6/20/2025 Approved ANTHONY RAMOS
Underground Mechanical 6/20/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 9/5/2025 Approved LUIS CASTRO
Final 9/5/2025 Corrections Issued LUIS CASTRO
Green Building Final 9/5/2025 Approved LUIS CASTRO
HVAC-Final 9/5/2025 Approved LUIS CASTRO
PLUMBING-Final 9/5/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 9/5/2025 Approved LUIS CASTRO
Final 9/12/2025 OK to Issue CofO LUIS CASTRO