10957-10959 W CALVERT ST 91606

Certificate Information: 10957-10959 W CALVERT ST 91606

Application / Permit
24016-20000-30178
Plan Check / Job No.
B24VN17218
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan - CONVERT EXISTING ATTACHED REC ROOM TO ADU (596 SF) PER CA GOVT CODE 65852.2(E)(1)(C) (BUILDING A) WITH NFPA 13D SPRINKLERS
Permit Issued
Issued on 8/29/2025
Issuing Office
Current Status
CofO Issued on 4/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 STARR CHEN
Corrections Issued 10/2/2024 STARR CHEN
Quality Review Completed 10/3/2024 EUGENE BARBEAU
Applicant returned to address corrections 10/23/2024 STARR CHEN
Applicant returned to address corrections 12/4/2024 STARR CHEN
Applicant returned to address corrections 3/14/2025 STARR CHEN
Plan Check Approved 8/27/2025 STARR CHEN
Issued 8/29/2025 APPLICANT
CofO in Progress 4/21/2026 JOSE AVILA
Permit Finaled 4/29/2026 RUBEN SALAS
CofO Issued 4/29/2026 RUBEN SALAS
Permit Finaled 4/29/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/14/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/15/2024 LEE GUILBEAUX
Sewer availability Cleared 11/15/2024 LEE GUILBEAUX
Hydrant and Access approval Cleared 2/18/2025 JOHN CONNEALLY
DAS Clearance Cleared 8/27/2025 STARR CHEN

Contact Information

Architect Lopez,, Craig Joseph; Lic. No.: NA14263       ,
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 9/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/11/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 9/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 9/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 9/16/2025 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 9/23/2025 Approved JOSE AVILA
HVAC-Rough 9/23/2025 Approved JOSE AVILA
ELECTRICAL-Rough 10/1/2025 Approved JOSE AVILA
PLUMBING-Rough 10/2/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 10/21/2025 Approved JOSE AVILA
Footing/Foundation/Slab 10/21/2025 Approved JOSE AVILA
Drywall Nailing 11/10/2025 Approved JOSE AVILA
Insulation 11/10/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 12/8/2025 Approved JOSE AVILA
Final 4/10/2026 OK to Issue CofO JOSE AVILA