7726 S WESTLAWN AVE 90045

Certificate Information: 7726 S WESTLAWN AVE 90045

Application / Permit
24016-20000-29967
Plan Check / Job No.
B24VN17029
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 10/3/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 ARTIN ZARUKIAN
Corrections Issued 9/28/2024 ARTIN ZARUKIAN
Building Plans Picked Up 9/30/2024 APPLICANT
Issued 10/3/2024 APPLICANT
CofO in Progress 3/17/2025 JESUS PINEDA
CofO Issued 3/17/2025 RICHARD STEINBACH
Permit Finaled 3/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/30/2024 DARIN LAM
Sewer availability Cleared 9/30/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 10/2/2024 BIAINA HARITUNIAN
Specific Plan Cleared 10/2/2024 RICHARD WOO
Grading Pre-Inspection Cleared 10/3/2024 MADISON O'DELL

Contact Information

Contractor Neo Builders And Design Inc; Lic. No.: 1114778-B 12005 ALBERS APT 233      NORTH HOLLYWOOD, CA 91607
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/22/2024 Partial Inspection BOBBY KEY
Underground Mechanical 10/30/2024 Partial Approval BOBBY KEY
Footing/Foundation/Slab 11/4/2024 Approved MICHAEL ALLEN
PLUMBING-Rough 11/15/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 11/20/2024 Corrections Issued MICHAEL ALLEN
HVAC-Rough 11/20/2024 Corrections Issued MICHAEL ALLEN
Deputy Wood Construction 11/25/2024 Conditional Approval TEMISTOCLES CAAL
Insulation 12/2/2024 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 12/2/2024 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 12/5/2024 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 12/6/2024 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Approved TEMISTOCLES CAAL
Insulation 12/6/2024 Conditional Approval TEMISTOCLES CAAL
Shower Pan 12/6/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 12/24/2024 Approved MICHAEL ALLEN
Green Building Rough 12/24/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 12/24/2024 Approved MICHAEL ALLEN
Pre-Inspection 2/11/2025 Partial Inspection TEMISTOCLES CAAL
HVAC-Final 3/11/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/14/2025 Approved JESUS PINEDA
ELECTRICAL-Final 3/14/2025 Approved JESUS PINEDA
Final 3/14/2025 OK to Issue CofO JESUS PINEDA
Green Building Final 3/14/2025 Approved JESUS PINEDA
PLUMBING-Final 3/14/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 3/14/2025 SGSOV Not Required JESUS PINEDA
Smoke Detectors 3/14/2025 Approved JESUS PINEDA