8905-8907 S KITTYHAWK AVE 90045

Certificate Information: 8905-8907 S KITTYHAWK AVE 90045

Application / Permit
24016-20000-29925
Plan Check / Job No.
B24VN16985
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF 1ST FLOOR OF EX 2-STORY SINGLE FAMILY DWELLING INTO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22. "COMPLY WITH DEPARTMENT ORDER effective date 07/25/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 2/6/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 HAYATO TSUCHIYA
Corrections Issued 9/25/2024 HAYATO TSUCHIYA
Building Plans Picked Up 9/27/2024 APPLICANT
Applicant returned to address corrections 1/29/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 2/6/2025 ALEC MOUSAKHANIAN
Issued 2/6/2025 APPLICANT
CofO in Progress 11/4/2025 ANDREW BEELI
Permit Finaled 2/4/2026 CLAUDIO MORENO
CofO Issued 2/4/2026 CLAUDIO MORENO
Permit Finaled 2/4/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 10/8/2024 BRENDEN HAWK
Sewer availability Cleared 10/8/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 10/16/2024 HISASHI KOBAYAKAWA
ZA Case Cleared 10/18/2024 NATHAN ROMINE
Specific Plan Cleared 11/8/2024 PEDRO AYALA

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/8/2025 Approved ANDREW BEELI
ELECTRICAL-Rough 8/28/2025 Corrections Issued ANDREW BEELI
HVAC-Rough 8/28/2025 Approved ANDREW BEELI
PLUMBING-Rough 8/28/2025 Approved ANDREW BEELI
Pre-Inspection 8/28/2025 Approved ANDREW BEELI
BUILDING-Rough-Frame 9/4/2025 Approved ANDREW BEELI
Final 9/4/2025 OK to Issue CofO ANDREW BEELI
Green Building Final 9/4/2025 Approved ANDREW BEELI
Green Building Rough 9/4/2025 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved ANDREW BEELI
Smoke Detectors 9/4/2025 Approved ANDREW BEELI
BUILDING-Rough-Frame 10/1/2025 Approved ANDREW BEELI
Final 10/1/2025 Partial Approval ANDREW BEELI
Green Building Final 10/1/2025 Approved ANDREW BEELI
Green Building Rough 10/1/2025 Approved ANDREW BEELI
ELECTRICAL-Final 1/21/2026 Approved ANDREW BEELI
ELECTRICAL-Rough 1/21/2026 Approved ANDREW BEELI
HVAC-Final 1/21/2026 Approved ANDREW BEELI
PLUMBING-Final 1/21/2026 Approved ANDREW BEELI