20728-20730 W STAGG ST 91306
Certificate Information: 20728-20730 W STAGG ST 91306
- Application / Permit
- 24016-20000-29884
- Plan Check / Job No.
- B24VN16957
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Attached garage to an (E) 2-story single family dwelling conversion to an atttached Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/2/2025
- Issuing Office
- Current Status
- CofO Issued on 3/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2024 | EDWIN ESPIN |
| Corrections Issued | 9/24/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 10/22/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 11/14/2024 | AMY GUEVARRA |
| Plan Check Approved | 11/22/2024 | KAVIAN REFAHI |
| Issued | 1/2/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | ROBERT GOLD |
| Permit Finaled | 3/5/2026 | JOHN JANSON |
| CofO Issued | 3/5/2026 | JOHN JANSON |
| Permit Finaled | 3/5/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/29/2024 | RYAN CASTRO |
Contact Information
| Architect | Patino, Lopez, Pablo Enrique; Lic. No.: C39772 | 2481 WAGNER ST #2 PASADENA, CA 91107 |
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/10/2025 | Approved | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 6/25/2025 | Conditional Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 6/25/2025 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 6/30/2025 | Corrections Issued | SCOTT SOBEL |
| Excavation/Setback/Form/Re-Bar | 8/1/2025 | Approved | SCOTT SOBEL |
| Insulation | 8/15/2025 | Partial Approval | ALEXANDER HANDY |
| Gas Test | 9/3/2025 | Partial Approval | ALEXANDER HANDY |
| Underground Mechanical | 9/10/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/19/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/19/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 9/19/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 9/19/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 9/19/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/2/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 10/2/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 10/2/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/2/2025 | Partial Approval | JEFFREY HARTLINE |
| Drywall Nailing | 10/7/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 10/7/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 10/15/2025 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 12/24/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 12/24/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 12/24/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 12/24/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 12/24/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 12/24/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/31/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 12/31/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 12/31/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 12/31/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Final | 12/31/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/31/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 12/31/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 12/31/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/26/2026 | Approved | TROY SANDERS |
| Final | 1/26/2026 | Corrections Issued | TROY SANDERS |
| Gas Test | 1/26/2026 | Approved | TROY SANDERS |
| Green Building Final | 1/26/2026 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 1/26/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 1/26/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 1/26/2026 | Approved | TROY SANDERS |
| Final | 2/26/2026 | OK to Issue CofO | ROBERT GOLD |
| Green Building Final | 2/26/2026 | Approved | ROBERT GOLD |