6500 S AVALON BLVD 90003
Certificate Information: 6500 S AVALON BLVD 90003
- Application / Permit
- 24016-20000-29581
- Plan Check / Job No.
- B24VN16729
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- Installation of a commercial rooftop solar PV array.
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Current Status
- Permit Finaled on 2/11/2026
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2024 | SERGIO MUNIZ |
| Corrections Issued | 10/28/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 1/14/2025 | PINANK PATEL |
| Plan Check Approved | 1/16/2025 | PINANK PATEL |
| Issued | 2/24/2025 | APPLICANT |
| Permit Finaled | 2/10/2026 | REGINA MENDEZ |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 11/4/2024 | ANACANY HURTADO |
| Miscellaneous | Cleared | 11/4/2024 | ANACANY HURTADO |
| Miscellaneous | Cleared | 11/7/2024 | ALEX VELA |
| Miscellaneous | Cleared | 11/7/2024 | ALEX VELA |
| Miscellaneous | Cleared | 11/7/2024 | ALEX VELA |
| ZA Case | Cleared | 11/7/2024 | ALEX VELA |
| Historic Resource Verification | Cleared | 11/12/2024 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 11/27/2024 | ELIZABETH GALLARDO |
Contact Information
| Contractor | Sun Sage Solar Llc; Lic. No.: 1099389-C10 | 215 QUAIL COURT ANTIOCH, CA 94509 |
| Engineer | Brown,, Samuel Mcfarland; Lic. No.: C91016 | 1801 S 825 W LEHI, UT 84043 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 8/8/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/8/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/3/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/3/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 2/6/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 2/6/2026 | Conditional Approval | DARRYL ARNOLD |
| Final | 2/10/2026 | Permit Finaled | REGINA MENDEZ |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Approved | REGINA MENDEZ |
| Smoke Detectors | 2/10/2026 | Approved | REGINA MENDEZ |