106 E 94TH ST 90003

Certificate Information: 106 E 94TH ST 90003

Application / Permit
24016-20000-29375
Plan Check / Job No.
B24VN16559
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 5/16/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2024 APPLICANT
Assigned to Plan Check Engineer 9/20/2024 ARTIN ZARUKIAN
Corrections Issued 9/21/2024 ARTIN ZARUKIAN
Building Plans Picked Up 9/23/2024 APPLICANT
Applicant returned to address corrections 4/8/2025 GIOVANNY CHAVEZ
Issued 5/16/2025 APPLICANT
CofO in Progress 1/13/2026 ANSON MAGLASANG
Permit Finaled 1/13/2026 ANSON MAGLASANG
CofO Issued 1/13/2026 ANSON MAGLASANG
Permit Finaled 1/13/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/22/2024 ABEL CASILLAS
Sewer availability Cleared 11/22/2024 ABEL CASILLAS
Construction near power lines Cleared 1/25/2025 RIDWAN HARDY
ZI Cleared 2/25/2025 DANIEL CORONADO
Community Plan Implem. Overlay Cleared 3/4/2025 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 4/20/2025 ABEL CASILLAS

Contact Information

Architect Humphries,, Douglas S; Lic. No.: C25559 12122 HARTSOOK STREET      VALLEY VILLAGE, CA 91607
Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2025 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 6/12/2025 Corrections Issued ANTHONY EGSON
Sewer 6/12/2025 Corrections Issued ANTHONY EGSON
Underground Mechanical 6/12/2025 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 6/20/2025 Partial Inspection JOHN KLARIN
Footing/Foundation/Slab 6/20/2025 Approved JOHN KLARIN
Gas Test 6/20/2025 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Approved JOHN KLARIN
Sewer 6/20/2025 Approved JOHN KLARIN
Underground Mechanical 6/20/2025 Partial Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/18/2025 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Partial Inspection JOHN KLARIN
Footing/Foundation/Slab 7/18/2025 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/14/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/14/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Corrections Issued ANTHONY EGSON
Green Building Rough 8/14/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 8/14/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 8/14/2025 Approved ANTHONY EGSON
Wood Frame 8/14/2025 Not Ready for Inspection ANTHONY EGSON
Special/Order Compliance 8/15/2025 Partial Inspection ANTHONY EGSON
BUILDING-Rough-Frame 8/22/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/22/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Approved ANTHONY EGSON
Green Building Rough 8/22/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 8/22/2025 Approved ANTHONY EGSON
Wood Frame 8/22/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 9/5/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Approved ANTHONY EGSON
Green Building Rough 9/5/2025 Approved ANTHONY EGSON
Wood Frame 9/5/2025 Approved ANTHONY EGSON
Insulation 9/12/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/12/2025 Approved ANTHONY EGSON
Drywall Nailing 9/19/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/19/2025 Approved ANTHONY EGSON
Shower Pan 10/10/2025 Not Ready for Inspection ANTHONY EGSON
Shower Pan 10/17/2025 Approved ANTHONY EGSON
Gas Test 10/28/2025 Approved ANTHONY EGSON
Shower Pan 10/28/2025 Approved ANTHONY EGSON
Underground Mechanical 10/28/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/31/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 12/5/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 12/5/2025 Approved ARTHUR NEGRETE
Service/Power Release 12/5/2025 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 12/5/2025 Approved ARTHUR NEGRETE
Green Building Final 12/26/2025 Partial Approval ARTHUR NEGRETE
HVAC-Final 12/26/2025 Approved ARTHUR NEGRETE
Final 12/29/2025 Corrections Issued ARTHUR NEGRETE
Final 12/31/2025 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 12/31/2025 Approved ARTHUR NEGRETE
Service/Power Release 12/31/2025 Not Ready for Inspection ARTHUR NEGRETE
Service/Power Release 1/2/2026 Approved ARTHUR NEGRETE