11280 N CORBIN AVE 91326
Certificate Information: 11280 N CORBIN AVE 91326
- Application / Permit
- 24016-20000-29364
- Plan Check / Job No.
- B24VN16549
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePlan: tenant improvement to existing one-story office building. No change in use/ occupancy/ exiting. No change in floor area.
- Permit Issued
- Issued on 8/15/2025
- Issuing Office
- Current Status
- Issued on 8/15/2025
Permit Application Status History
| Submitted | 9/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | CARLOS MONTES |
| Corrections Issued | 9/21/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 10/9/2024 | AUNG SOE |
| Plan Check Approved | 10/15/2024 | AUNG SOE |
| Issued | 8/15/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Kellogg,, Mark Robert; Lic. No.: NA22989 | , |
| Contractor | R C I Builders Inc; Lic. No.: 835114-B | , |
| Contractor | Rci Builders Inc; Lic. No.: 835114-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 9/24/2025 | Partial Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 9/29/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 10/16/2025 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 10/30/2025 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 11/3/2025 | Approved | KENNETH ROBERTS |
| Wood Frame | 11/13/2025 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 11/26/2025 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 12/17/2025 | Partial Approval | EDWIN GREGORYONA |
| T-Bar Ceiling | 12/22/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Insulation | 1/23/2026 | Approved | GREGORY POMISH |
| Final | 2/23/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Final | 2/23/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Not Ready | EDWIN GREGORYONA |
| Smoke Detectors | 2/23/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Special/Order Compliance | 2/23/2026 | No Access for Inspection | SEAN GRIFFITH |
| Final | 3/12/2026 | Conditional Approval | EDWIN GREGORYONA |
| Green Building Final | 3/12/2026 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 3/12/2026 | Approved | EDWIN GREGORYONA |
| Final | 3/16/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Pre-Inspection | 3/18/2026 | No Access for Inspection | EDWIN GREGORYONA |
| Final | 4/22/2026 | Not Ready for Inspection | BRIAN KELLY |
| Final | 5/7/2026 | Conditional Approval | EDWIN GREGORYONA |