1201-1203 E 55TH ST 90011
Certificate Information: 1201-1203 E 55TH ST 90011
- Application / Permit
- 24016-20000-29239
- Plan Check / Job No.
- B24VN16422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: CONVERT (E) PORTION OF 2-STORY DUPLEX INTO A (N) ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH CA Govt. Code 65852.2(e)(1)(C) PER ENGINEERING
- Permit Issued
- Issued on 8/8/2025
- Issuing Office
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | ALFRED RAMIREZ |
| Corrections Issued | 10/9/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 10/16/2024 | STEVEN KIM |
| Applicant returned to address corrections | 1/10/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 7/29/2025 | ALFRED RAMIREZ |
| Issued | 8/8/2025 | APPLICANT |
| CofO in Progress | 1/29/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
| CofO Issued | 1/30/2026 | DEROLD HAUFF |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 1/23/2025 | JASON CHAN |
| ZA Case | Cleared | 1/23/2025 | JASON CHAN |
| Address approval | Cleared | 5/8/2025 | CELINA MORENO |
| Sewer availability | Cleared | 5/8/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2025 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 7/15/2025 | MANERI ROMAN |
| ZI | Cleared | 7/15/2025 | MANERI ROMAN |
| Tenant Habitability Plan | Cleared | 7/21/2025 | KORNEL LELEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Flores,, Mario Baldonade; Lic. No.: C90813 | 4830 PARKS AVE APT 101 LA MESA, CA 91942 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/7/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 11/19/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 11/19/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/27/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Final | 1/29/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/29/2026 | Approved | ALEJANDRO DE ARTOLA |