10441 N O'MELVENY AVE 91331

Certificate Information: 10441 N O'MELVENY AVE 91331

Application / Permit
24016-20000-29231
Plan Check / Job No.
B24VN16405
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 16'0"X20'0" PATIO COVER THAT IS ATTACHED TO THE EXSITNG SINGLE FAMILY DWELLING TO A RECREATION ROOM.
Permit Issued
Issued on 11/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 MARVEL DELACRUZ
Corrections Issued 9/26/2024 MARVEL DELACRUZ
Quality Review Completed 9/30/2024 JASON HEALEY
Building Plans Picked Up 10/2/2024 APPLICANT
Applicant returned to address corrections 11/20/2024 MARVEL DELACRUZ
Plan Check Approved 11/27/2024 MARVEL DELACRUZ
Issued 11/27/2024 APPLICANT
CofO in Progress 9/5/2025 MICHEL ABAJAN
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/5/2024 RYAN CASTRO
Sewer availability Cleared 11/5/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/6/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/14/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/17/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 1/17/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 3/25/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/25/2025 Approved MICHEL ABAJAN
Gas Test 3/25/2025 Approved MICHEL ABAJAN
Green Building Rough 3/25/2025 Approved MICHEL ABAJAN
HVAC-Rough 3/25/2025 Approved MICHEL ABAJAN
METHANE-Rough 3/25/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 3/25/2025 Approved MICHEL ABAJAN
Insulation 4/1/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/1/2025 Approved MICHEL ABAJAN
Drywall Nailing 4/14/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/14/2025 Partial Inspection MICHEL ABAJAN
Shower Pan 4/14/2025 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 8/12/2025 Approved MICHEL ABAJAN
Final 8/12/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 8/12/2025 Approved MICHEL ABAJAN
HVAC-Final 8/12/2025 Approved MICHEL ABAJAN
PLUMBING-Final 8/12/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 8/12/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/12/2025 Not Ready for Inspection MICHEL ABAJAN
Final 8/29/2025 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 8/29/2025 Approved MICHEL ABAJAN
Final 9/3/2025 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved MICHEL ABAJAN