8544 N VAN NUYS BLVD 91402

Certificate Information: 8544 N VAN NUYS BLVD 91402

Application / Permit
24016-20000-29224
Plan Check / Job No.
B24VN16392
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Change of use from (E) video game arcade to restaurant
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2024 APPLICANT
Assigned to Plan Check Engineer 9/18/2024 SHANGQIN XIE
Corrections Issued 9/18/2024 SHANGQIN XIE
Applicant returned to address corrections 11/4/2024 SHANGQIN XIE
Plan Check Approved 11/6/2024 SHANGQIN XIE
Issued 11/7/2024 APPLICANT
CofO in Progress 12/31/2025 ANDREW DORSO
Permit Finaled 1/2/2026 JEFFREY DURAN
CofO Issued 1/2/2026 JEFFREY DURAN
Permit Finaled 1/2/2026 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/19/2024 CARLOS AGUILERA
Sewer availability Cleared 9/19/2024 CARLOS AGUILERA
"Q" conditions Cleared 9/24/2024 ALEX VELA
ZA Case Cleared 9/24/2024 ALEX VELA
ZA Case Cleared 9/24/2024 ALEX VELA
Supp. Use District POD/CDO/TDO Cleared 10/4/2024 OLGA AYALA
Food Service Establishment Cleared 10/29/2024 BOGDAN SERBANESCU
Food establishment approval Cleared 10/31/2024 LACDHS APPROVED

Contact Information

Architect Matthews,, Erik; Lic. No.: C32764 2712 SE 47TH AVENUE      PORTLAND, OR 97206
Contractor Pink Hammer Construction; Lic. No.: 1076292-B       ,

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Masonry Wall/Backfill 1/7/2025 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 3/24/2025 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 4/4/2025 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/10/2025 Approved KENNETH ROBERTS
T-Bar Ceiling 9/30/2025 Not Ready for Inspection ANDREW DORSO
T-Bar Ceiling 10/6/2025 Not Ready for Inspection ANDREW DORSO
T-Bar Ceiling 11/14/2025 Approved ANDREW DORSO
Final 12/23/2025 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 12/23/2025 Not Ready for Inspection BRIAN KELLY
Final 12/30/2025 Partial Approval ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Approved ANDREW DORSO
Smoke Detectors 12/30/2025 Approved ANDREW DORSO
Final 12/31/2025 OK to Issue CofO ANDREW DORSO