8544 N VAN NUYS BLVD 91402
Certificate Information: 8544 N VAN NUYS BLVD 91402
- Application / Permit
- 24016-20000-29224
- Plan Check / Job No.
- B24VN16392
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of use from (E) video game arcade to restaurant
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Current Status
- CofO Issued on 1/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2024 | SHANGQIN XIE |
| Corrections Issued | 9/18/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/4/2024 | SHANGQIN XIE |
| Plan Check Approved | 11/6/2024 | SHANGQIN XIE |
| Issued | 11/7/2024 | APPLICANT |
| CofO in Progress | 12/31/2025 | ANDREW DORSO |
| Permit Finaled | 1/2/2026 | JEFFREY DURAN |
| CofO Issued | 1/2/2026 | JEFFREY DURAN |
| Permit Finaled | 1/2/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/19/2024 | CARLOS AGUILERA |
| "Q" conditions | Cleared | 9/24/2024 | ALEX VELA |
| ZA Case | Cleared | 9/24/2024 | ALEX VELA |
| ZA Case | Cleared | 9/24/2024 | ALEX VELA |
| Supp. Use District POD/CDO/TDO | Cleared | 10/4/2024 | OLGA AYALA |
| Food Service Establishment | Cleared | 10/29/2024 | BOGDAN SERBANESCU |
| Food establishment approval | Cleared | 10/31/2024 | LACDHS APPROVED |
Contact Information
| Architect | Matthews,, Erik; Lic. No.: C32764 | 2712 SE 47TH AVENUE PORTLAND, OR 97206 |
| Contractor | Pink Hammer Construction; Lic. No.: 1076292-B | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall/Backfill | 1/7/2025 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/24/2025 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 4/4/2025 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 4/10/2025 | Approved | KENNETH ROBERTS |
| T-Bar Ceiling | 9/30/2025 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 10/6/2025 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 11/14/2025 | Approved | ANDREW DORSO |
| Final | 12/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 12/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 12/30/2025 | Partial Approval | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 12/30/2025 | Approved | ANDREW DORSO |
| Final | 12/31/2025 | OK to Issue CofO | ANDREW DORSO |