8450 N AURA AVE 91324
Certificate Information: 8450 N AURA AVE 91324
- Application / Permit
- 24016-20000-29223
- Plan Check / Job No.
- B24VN16388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE / STORAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | SARKIS HARABEDIAN |
| Corrections Issued | 9/21/2024 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/25/2024 | SARKIS HARABEDIAN |
| Issued | 12/27/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | JEFFREY HARTLINE |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
| CofO Issued | 4/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/23/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/30/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/31/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/9/2025 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/9/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/9/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/18/2025 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 1/18/2025 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 1/18/2025 | Partial Approval | HENRY KIM |
| Shower Pan | 1/18/2025 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 1/18/2025 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 1/18/2025 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 1/27/2025 | Not Ready for Inspection | SCOTT SOBEL |
| HVAC-Rough | 1/27/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Interior/Exterior Lathing | 1/27/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Shower Pan | 1/27/2025 | Partial Approval | SCOTT SOBEL |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 1/29/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 1/29/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 1/29/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 1/29/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 2/3/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 2/6/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 5/19/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 5/19/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Smoke Detectors | 5/19/2025 | Approved | JEFFREY HARTLINE |
| Final | 6/5/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 6/5/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 6/5/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Final | 6/18/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 6/18/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 6/18/2025 | Approved | JEFFREY HARTLINE |