22235 W SATICOY ST 91303
Certificate Information: 22235 W SATICOY ST 91303
- Application / Permit
- 24016-20000-29163
- Plan Check / Job No.
- B24VN16286
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/7/2024
- Issuing Office
- Current Status
- CofO Corrected on 2/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | MADISON ODELL |
| Corrections Issued | 9/19/2024 | MADISON ODELL |
| Building Plans Picked Up | 9/19/2024 | APPLICANT |
| Applicant returned to address corrections | 9/26/2024 | ANGELICA DAVE |
| Plan Check Approved | 10/7/2024 | OMAR GARNICA |
| Issued | 10/7/2024 | APPLICANT |
| CofO in Progress | 2/11/2025 | JEFFREY HARTLINE |
| CofO Issued-Status Void | 2/20/2025 | JOHN JANSON |
| Permit Finaled-Status Void | 2/20/2025 | JOHN JANSON |
| Re-Activate Permit | 2/21/2025 | JOHN JANSON |
| Permit Finaled | 2/21/2025 | JOHN JANSON |
| CofO Corrected | 2/21/2025 | JOHN JANSON |
| Permit Finaled | 2/21/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 9/20/2024 | EDGAR ALCARAZ |
| Tract Map conditions | Cleared | 9/24/2024 | DORIAN AGUILAR |
| Hydrant and Access approval | Cleared | 10/3/2024 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/16/2024 | Conditional Approval | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 10/21/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/21/2024 | Approved | JEFFREY HARTLINE |
| Deputy Wood Construction | 11/7/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 11/8/2024 | No Result Entered | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Partial Approval | JEFFREY HARTLINE |
| Sewer | 11/18/2024 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 11/18/2024 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 11/25/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 11/25/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 11/25/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 12/2/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 12/6/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/6/2024 | Partial Approval | JEFFREY HARTLINE |
| Final | 1/27/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 1/27/2025 | Approved | JEFFREY HARTLINE |
| Final | 2/3/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 2/3/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 2/10/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 2/10/2025 | Approved | JEFFREY HARTLINE |