19407 W CALVERT ST 91335

Certificate Information: 19407 W CALVERT ST 91335

Application / Permit
24016-20000-28959
Plan Check / Job No.
B24VN16091
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERSION OF THE (E) DET GARAGE INTO A (N) ADU (403 SQ.FT) PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2024 APPLICANT
Assigned to Plan Check Engineer 9/16/2024 LUISANGEL VALENZUELA
Corrections Issued 9/17/2024 LUISANGEL VALENZUELA
Plan Check Approved 10/2/2024 LUISANGEL VALENZUELA
Issued 10/2/2024 APPLICANT
CofO in Progress 1/14/2025 ALEXANDER HANDY
Permit Finaled 2/6/2025 JOHN JANSON
CofO Issued 2/6/2025 JOHN JANSON
Permit Finaled 2/6/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/19/2024 RYAN CASTRO
Construction near power lines Cleared 9/19/2024 WALTER RAMIREZ
Sewer availability Cleared 9/19/2024 RYAN CASTRO
ZI Cleared 9/19/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 9/20/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/10/2024 Conditional Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 10/17/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/17/2024 Partial Approval ARUTYUN MADATYAN
Sewer 10/17/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 10/28/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/28/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/31/2024 Approved ARUTYUN MADATYAN
Green Building Rough 10/31/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 10/31/2024 Partial Approval ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 10/31/2024 Approved ARUTYUN MADATYAN
Insulation 11/5/2024 Corrections Issued ALEXANDER HANDY
Shower Pan 11/5/2024 Approved ALEXANDER HANDY
Insulation 11/13/2024 Approved KRISTEN CAUSEY
Drywall Nailing 11/19/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 11/19/2024 Approved ALEXANDER HANDY
Gas Test 12/19/2024 Approved CHRIS CHRISTENSEN
Service/Power Release 12/19/2024 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 12/23/2024 Not Ready for Inspection ALEXANDER HANDY
Final 12/23/2024 Corrections Issued ALEXANDER HANDY
Green Building Final 12/23/2024 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 12/23/2024 Approved ALEXANDER HANDY
PLUMBING-Final 12/23/2024 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 12/23/2024 Approved ALEXANDER HANDY
ELECTRICAL-Final 1/8/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 1/8/2025 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 1/8/2025 Approved JEFFREY HARTLINE
HVAC-Final 1/8/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 1/8/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 1/14/2025 Approved ALEXANDER HANDY
Final 1/14/2025 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 1/14/2025 Approved ALEXANDER HANDY
PLUMBING-Final 1/14/2025 Approved ALEXANDER HANDY
Service/Power Release 1/14/2025 Approved ALEXANDER HANDY
Special/Order Compliance 1/14/2025 Partial Inspection JUAN ALVARADO