16501 W VINCENNES ST 91343
Certificate Information: 16501 W VINCENNES ST 91343
- Application / Permit
- 24016-20000-28946
- Plan Check / Job No.
- B24VN16084
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTERIOR/INTERIOR REMODEL TO (E) SFD.
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/29/2025
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2024 | JESSE ARELLANO |
| Corrections Issued | 9/16/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 9/20/2024 | APPLICANT |
| Applicant returned to address corrections | 10/29/2024 | SERGIO MUNIZ |
| Plan Check Approved | 10/30/2024 | SERGIO MUNIZ |
| Issued | 10/30/2024 | APPLICANT |
| Permit Finaled | 9/29/2025 | GAREN HAYRAPETYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/22/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 10/30/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Venegas Reyes Construction; Lic. No.: 660507-B | 20324 AETNA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/12/2024 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 11/20/2024 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 11/20/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/20/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/12/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/20/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 12/30/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/30/2024 | Partial Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 12/30/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 12/30/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/30/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/30/2024 | Partial Inspection | KEVIN BERBERYAN |
| Drywall Nailing | 1/9/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 1/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 2/3/2025 | Approved | SALVADOR MARTINEZ |
| Final | 9/29/2025 | Permit Finaled | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 9/29/2025 | Approved | GAREN HAYRAPETYAN |