4237 N BRUNSWICK AVE 90039
Certificate Information: 4237 N BRUNSWICK AVE 90039
- Application / Permit
- 24016-20000-28861
- Plan Check / Job No.
- B24VN16020
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 9/14/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/23/2024 | APPLICANT |
| Plan Check Approved | 10/9/2024 | YAQUB MIRZA |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 10/16/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 9/20/2024 | JESSICA OPINION |
| ZI | Cleared | 9/24/2024 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2024 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/8/2024 | Conditional Approval | ANTHONY RAMOS |
| Footing/Foundation/Slab | 11/22/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/14/2025 | Partial Approval | THOMAS LOGRASSO |
| Wood Frame | 2/13/2025 | Partial Inspection | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 2/14/2025 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 3/12/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 3/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 3/17/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Insulation | 3/20/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 3/20/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 4/2/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 4/4/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 4/4/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 4/8/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 4/29/2025 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 5/5/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 5/5/2025 | Approved | REGINA MENDEZ |
| Sewer | 5/20/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 9/2/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 9/2/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 9/30/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Service/Power Release | 9/30/2025 | Partial Approval | NICHOLAS LOPEZ |
| Smoke Detectors | 9/30/2025 | Approved | NICHOLAS LOPEZ |
| Final | 10/15/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 10/15/2025 | Approved | NICHOLAS LOPEZ |