6308-6310 N KRAFT AVE 91606
Certificate Information: 6308-6310 N KRAFT AVE 91606
- Application / Permit
- 24016-20000-28843
- Plan Check / Job No.
- B24VN15996
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) ATTACHED PATIO COVER AND GARAGE INTO A (N) 24'-0" x 16'-0" 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT PER ENGINEERING
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | ALFRED RAMIREZ |
| Corrections Issued | 9/23/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 9/24/2024 | STEVEN KIM |
| Building Plans Picked Up | 10/4/2024 | APPLICANT |
| Plan Check Approved | 12/17/2024 | ALFRED RAMIREZ |
| Issued | 12/17/2024 | APPLICANT |
| CofO in Progress | 2/20/2026 | ROBERTO PALACIOS-LOPEZ |
| No Progress | 2/24/2026 | RAUL OLAGI |
| CofO in Progress | 2/24/2026 | RAUL OLAGI |
| CofO in Progress | 3/23/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 4/10/2026 | RUBEN SALAS |
| CofO Issued | 4/10/2026 | RUBEN SALAS |
| Permit Finaled | 4/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/17/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 10/22/2024 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/10/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 9/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/9/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 9/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/15/2025 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 10/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 1/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 1/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 1/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 1/27/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 1/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 2/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/3/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV No Gas | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/3/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/19/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/19/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/19/2026 | Approved | ROBERTO PALACIOS-LOPEZ |