10922 N PETIT AVE 91344

Certificate Information: 10922 N PETIT AVE 91344

Application / Permit
24016-20000-28781
Plan Check / Job No.
B24VN15958
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Det. Garage conversion at rear of the lot to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work per Wood Frame Prescriptive Provisions
Permit Issued
Issued on 11/19/2024
Issuing Office
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/27/2024 EDWIN ESPIN
Corrections Issued 9/28/2024 EDWIN ESPIN
Applicant returned to address corrections 11/4/2024 EDWIN ESPIN
Applicant returned to address corrections 11/18/2024 EDWIN ESPIN
Plan Check Approved 11/19/2024 YASHAR EMAMI
Issued 11/19/2024 APPLICANT
CofO in Progress 7/29/2025 CHRISTOPHER ROJAS
Permit Finaled 8/5/2025 RUBEN SALAS
CofO Issued 8/5/2025 RUBEN SALAS
Permit Finaled 8/5/2025 RUBEN SALAS

Permit Application Clearance Information

Construction within easement Cleared 10/8/2024 WALTER RAMIREZ
Address approval Cleared 10/30/2024 RYAN CASTRO
Sewer availability Cleared 10/30/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/8/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Chaaya,, Danny Camille; Lic. No.: NA45555       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/21/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 11/21/2024 Partial Approval JAVIER RAMOS JR
Underground Mechanical 11/21/2024 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 11/22/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 12/16/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 12/16/2024 Approved JAVIER RAMOS JR
HVAC-Rough 12/16/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 12/16/2024 Approved JAVIER RAMOS JR
Pre-Inspection 12/16/2024 Approved JAVIER RAMOS JR
Sewer 12/16/2024 Approved JAVIER RAMOS JR
Underground Mechanical 12/16/2024 Approved JAVIER RAMOS JR
Wood Frame 12/16/2024 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 12/24/2024 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 12/24/2024 Approved JACK KARGODORIAN
Insulation 12/24/2024 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 12/24/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Partial Approval DAVID ANDERSON
Interior/Exterior Lathing 1/14/2025 Approved LOUIS ESCOTO
Shower Pan 1/14/2025 Approved LOUIS ESCOTO
Drywall Nailing 1/27/2025 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 7/23/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 7/23/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 7/23/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/28/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 7/28/2025 Approved CHRISTOPHER ROJAS
Final 7/28/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 7/28/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 7/28/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 7/28/2025 Approved CHRISTOPHER ROJAS