10401 N KEOKUK AVE 91311

Certificate Information: 10401 N KEOKUK AVE 91311

Application / Permit
24016-20000-28718
Plan Check / Job No.
B24VN15898
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: MAJOR REMODEL TO (E) SFD. REMODEL KITCHEN, BEDROOMS AND BATHROOMS. WORK DONE PER ENGINEER DEISGN.
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
Issued on 10/9/2024

Permit Application Status History

Submitted 9/10/2024 APPLICANT
Assigned to Plan Check Engineer 9/13/2024 KAMYAR EMAMI
Corrections Issued 9/16/2024 KAMYAR EMAMI
Applicant returned to address corrections 9/30/2024 KAMYAR EMAMI
Applicant returned to address corrections 10/2/2024 KAMYAR EMAMI
Plan Check Approved 10/8/2024 MIROOSH KHACHATOORIAN
Issued 10/9/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 9/24/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/25/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 9/25/2024 CHARLES POWELL

Contact Information

Architect Verdugo,, Emilio Amado; Lic. No.: NA33263       ,
Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/22/2024 Approved DAVID SCANTLIN
Deputy Wood Construction 10/23/2024 Conditional Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 2/28/2025 No Access for Inspection DAVID SCANTLIN
HVAC-Rough 2/28/2025 No Access for Inspection DAVID SCANTLIN
PLUMBING-Rough 2/28/2025 No Access for Inspection DAVID SCANTLIN
HVAC-Rough 3/6/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 3/6/2025 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/28/2025 Corrections Issued SCOTT SOBEL
Interior/Exterior Lathing 3/28/2025 Partial Approval SCOTT SOBEL
BUILDING-Rough-Frame 4/2/2025 Approved DAVID SCANTLIN
ELECTRICAL-Rough 4/2/2025 Approved DAVID SCANTLIN
Insulation 4/4/2025 Approved KRISTEN CAUSEY
Drywall Nailing 4/10/2025 Approved ARUTYUN MADATYAN
Shower Pan 4/17/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/29/2025 Approved HENRY KIM
Gas Test 7/21/2025 Approved DAVID SCANTLIN