8037 N WILKINSON AVE 91605

Certificate Information: 8037 N WILKINSON AVE 91605

Application / Permit
24016-20000-28659
Plan Check / Job No.
B24VN15821
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE & STORAGE BUILDING INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 4/15/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 LUISANGEL VALENZUELA
Building Plans Picked Up 9/12/2024 APPLICANT
Corrections Issued 9/24/2024 LUISANGEL VALENZUELA
Plan Check Approved 12/19/2024 HAYATO TSUCHIYA
Plan Check Approved 12/19/2024 HAYATO TSUCHIYA
Issued 4/15/2025 APPLICANT
CofO in Progress 1/15/2026 MATTHEW NELSON
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/13/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 9/13/2024 EDGAR ALCARAZ
Sewer availability Cleared 9/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/18/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/21/2025 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 4/21/2025 Corrections Issued DAVID MATSON
Green Building Rough 4/21/2025 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 4/21/2025 Corrections Issued DAVID MATSON
Deputy Drilled-In Anchors 4/23/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/23/2025 Partial Approval WILLIAM WREN
PLUMBING-Rough 4/23/2025 Partial Approval WILLIAM WREN
Sewer 4/23/2025 Corrections Issued WILLIAM WREN
Special/Order Compliance 4/23/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 4/29/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/29/2025 Partial Approval NICHOLAS TROWBRIDGE
Sewer 4/29/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 5/7/2025 Corrections Issued NICHOLAS TROWBRIDGE
Sewer 5/7/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/31/2025 Corrections Issued MATTHEW NELSON
HVAC-Rough 7/31/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 7/31/2025 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 8/6/2025 Approved MATTHEW NELSON
HVAC-Rough 8/6/2025 Approved MATTHEW NELSON
PLUMBING-Rough 8/6/2025 Approved MATTHEW NELSON
Insulation 8/12/2025 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 8/12/2025 Partial Approval MATTHEW NELSON
Insulation 8/14/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Approved MATTHEW NELSON
Drywall Nailing 8/26/2025 Approved MATTHEW NELSON
Green Building Rough 8/26/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/30/2025 Approved MATTHEW NELSON
Shower Pan 9/30/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/4/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 12/4/2025 Approved MATTHEW NELSON
Final 12/4/2025 Corrections Issued MATTHEW NELSON
Green Building Final 12/4/2025 Corrections Issued MATTHEW NELSON
HVAC-Final 12/4/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Final 12/4/2025 Partial Approval MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 12/4/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 12/11/2025 Approved MATTHEW NELSON
Final 12/11/2025 Corrections Issued MATTHEW NELSON
Green Building Final 12/11/2025 Corrections Issued MATTHEW NELSON
HVAC-Final 12/11/2025 Partial Approval MATTHEW NELSON
PLUMBING-Final 12/11/2025 Partial Approval MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved MATTHEW NELSON
Final 1/14/2026 OK to Issue CofO MATTHEW NELSON
Green Building Final 1/14/2026 Approved MATTHEW NELSON
Service/Power Release 1/14/2026 Approved MATTHEW NELSON