16661-16663 W ITASCA ST 91343

Certificate Information: 16661-16663 W ITASCA ST 91343

Application / Permit
24016-20000-28555
Plan Check / Job No.
B24VN15711
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. CONVERT EXISTING GARAGE TO AN ADU PER STATE LAW
Permit Issued
Issued on 4/12/2025
Issuing Office
Current Status
CofO Issued on 12/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/11/2024 ALEXANDER JOO
Corrections Issued 9/12/2024 ALEXANDER JOO
Applicant returned to address corrections 9/23/2024 SUNMIN LEE
Applicant returned to address corrections 10/3/2024 JOSEPH RAFOLS
Plan Check Approved 10/4/2024 JOSEPH RAFOLS
Issued 4/12/2025 APPLICANT
CofO in Progress 11/19/2025 GAREN HAYRAPETYAN
Permit Finaled 12/11/2025 RUBEN SALAS
CofO Issued 12/11/2025 RUBEN SALAS
Permit Finaled 12/11/2025 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 9/12/2024 STEVEN WECHSLER
Grading Pre-Inspection Cleared 9/13/2024 CHARLES POWELL
Address approval Cleared 9/16/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/16/2024 RYAN CASTRO
Sewer availability Cleared 9/16/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/21/2025 Partial Approval SALVADOR MARTINEZ
Deputy Drilled-In Anchors 6/9/2025 Conditional Approval RAUL OLAGI
Deputy Drilled-In Anchors 6/16/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/16/2025 Approved KEVIN BERBERYAN
Underground Mechanical 6/16/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 8/18/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 8/18/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 8/18/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 8/18/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/18/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/27/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 8/27/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 8/27/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 8/27/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 8/27/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 9/8/2025 Approved GAREN HAYRAPETYAN
Deputy Wood Construction 9/8/2025 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/8/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 9/8/2025 Approved GAREN HAYRAPETYAN
Insulation 9/8/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 9/8/2025 Partial Approval GAREN HAYRAPETYAN
Shower Pan 9/8/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 9/17/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 9/17/2025 Approved GAREN HAYRAPETYAN
Final 11/19/2025 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 11/19/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/19/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 11/19/2025 Approved GAREN HAYRAPETYAN