8312 S HOLY CROSS PL 90045

Certificate Information: 8312 S HOLY CROSS PL 90045

Application / Permit
24016-20000-28548
Plan Check / Job No.
B24VN15702
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) .ALL WORK DONE PER WFPP.
Permit Issued
Issued on 9/18/2024
Issuing Office
Current Status
CofO Issued on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/11/2024 ARTIN ZARUKIAN
Corrections Issued 9/16/2024 ARTIN ZARUKIAN
Building Plans Picked Up 9/16/2024 APPLICANT
Plan Check Approved 9/18/2024 YAQUB MIRZA
Issued 9/18/2024 APPLICANT
CofO in Progress 2/12/2025 TEMISTOCLES CAAL
Permit Finaled 2/13/2025 RICHARD STEINBACH
CofO Issued 2/13/2025 RICHARD STEINBACH
Permit Finaled 2/13/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/14/2024 LIAM ODONOVAN
Sewer availability Cleared 9/14/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 9/16/2024 KIMBERLY HERNANDEZ
Specific Plan Cleared 9/17/2024 RICHARD WOO
Grading Pre-Inspection Cleared 9/18/2024 ARTIN ZARUKIAN

Contact Information

Contractor Neo Builders And Design Inc; Lic. No.: 1114778-B 12005 ALBERS APT 233      NORTH HOLLYWOOD, CA 91607
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/22/2024 Partial Approval BOBBY KEY
Footing/Foundation/Slab 10/28/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 11/12/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 11/13/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 11/13/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/19/2024 Not Ready for Inspection TEMISTOCLES CAAL
Green Building Rough 11/19/2024 Approved TEMISTOCLES CAAL
Insulation 11/19/2024 Conditional Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 11/19/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/21/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Approved TEMISTOCLES CAAL
Insulation 11/21/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 11/25/2024 Approved TEMISTOCLES CAAL
Shower Pan 11/25/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 11/26/2024 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 12/2/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 1/30/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 1/30/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 1/30/2025 Approved TEMISTOCLES CAAL
Smoke Detectors 1/30/2025 Approved TEMISTOCLES CAAL
Final 2/11/2025 OK to Issue CofO TEMISTOCLES CAAL
Green Building Final 2/11/2025 Approved TEMISTOCLES CAAL
HVAC-Final 2/11/2025 Approved TEMISTOCLES CAAL