7329-7331 N BALBOA BLVD 91406
Certificate Information: 7329-7331 N BALBOA BLVD 91406
- Application / Permit
- 24016-20000-28370
- Plan Check / Job No.
- B24VN15534
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT IRREG SHAPED (836 SF) PORTION OF SFD TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 11/26/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 9/12/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/16/2024 | APPLICANT |
| Issued | 11/26/2024 | APPLICANT |
| CofO in Progress | 12/3/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 12/4/2025 | RUBEN SALAS |
| CofO Issued | 12/4/2025 | RUBEN SALAS |
| Permit Finaled | 12/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 11/14/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2024 | CARLOS RAMIREZ |
Contact Information
| Architect | Ramezani,, Kemal; Lic. No.: C19925 | 23838 HARBOR VISTA DRIVE MALIBU, CA 90265 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Pre-Inspection | 1/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 3/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 3/10/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 3/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Drywall Nailing | 3/13/2025 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/23/2025 | OK to Issue CofO | SALVADOR MARTINEZ |