4640 N WILLOW CREST AVE 91602
Certificate Information: 4640 N WILLOW CREST AVE 91602
- Application / Permit
- 24016-20000-28333
- Plan Check / Job No.
- B24VN15468
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 9/16/2024 | ARTIN ZARUKIAN |
| Issued | 9/16/2024 | APPLICANT |
| Building Plans Picked Up | 9/16/2024 | APPLICANT |
| CofO in Progress | 5/12/2025 | JAVIER RAMOS JR |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
| CofO Issued | 6/5/2025 | RUBEN SALAS |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 9/16/2024 | RYAN CASTRO |
Contact Information
| Contractor | Neo Builders And Design Inc; Lic. No.: 1114778-B | 12005 ALBERS APT 233 NORTH HOLLYWOOD, CA 91607 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 11/21/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 11/21/2024 | Approved | MISAEL ESPARZA |
| Sewer | 11/21/2024 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/3/2024 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 12/9/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 12/16/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/6/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/6/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/6/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/6/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/27/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/27/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 1/30/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 2/6/2025 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 2/6/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 2/10/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 2/19/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/17/2025 | Partial Inspection | JAVIER RAMOS JR |
| Final | 4/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Final | 4/17/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/17/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/17/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 5/1/2025 | Approved | JAVIER RAMOS JR |
| Final | 5/1/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 5/1/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 5/1/2025 | Approved | JAVIER RAMOS JR |