18240-18242 W RAYEN ST 91325
Certificate Information: 18240-18242 W RAYEN ST 91325
- Application / Permit
- 24016-20000-28118
- Plan Check / Job No.
- B24VN15269
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING ATTACHED GARAGE (355 S.F) AND BREEZEWAY (140 SF) TO NEW JUNIOR ACCESSORY DWELLING UNIT (495 SF) PER GCS 65852.2(e)(1)(A) AND 65852.22 .
- Permit Issued
- Issued on 9/25/2024
- Issuing Office
- Current Status
- CofO Issued on 3/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/7/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 9/25/2024 | ISIS ARGUETA |
| Issued | 9/25/2024 | APPLICANT |
| CofO in Progress | 3/5/2025 | KRISTEN BEVERIDGE |
| Permit Finaled | 3/7/2025 | JOHN JANSON |
| CofO Issued | 3/7/2025 | JOHN JANSON |
| Permit Finaled | 3/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/17/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/15/2024 | Partial Approval | KRISTEN CAUSEY |
| Deputy Drilled-In Anchors | 10/18/2024 | Conditional Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 10/21/2024 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 12/10/2024 | Approved | KRISTEN CAUSEY |
| HVAC-Rough | 12/10/2024 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 12/10/2024 | Approved | KRISTEN CAUSEY |
| Pre-Inspection | 12/12/2024 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/20/2024 | Approved | DAVID SCANTLIN |
| Green Building Final | 12/20/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 12/20/2024 | Approved | DAVID SCANTLIN |
| Insulation | 12/20/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/20/2024 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 12/23/2024 | Approved | DAVID SCANTLIN |
| Shower Pan | 1/3/2025 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 1/7/2025 | Approved | KRISTEN CAUSEY |
| Sewer | 1/13/2025 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 1/13/2025 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 2/19/2025 | Approved | SEAN WIRCH |
| HVAC-Final | 2/19/2025 | Approved | SEAN WIRCH |
| PLUMBING-Final | 2/19/2025 | Approved | SEAN WIRCH |
| Final | 2/25/2025 | Partial Inspection | KRISTEN CAUSEY |
| Green Building Final | 2/25/2025 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | KRISTEN CAUSEY |
| Smoke Detectors | 2/25/2025 | Approved | KRISTEN CAUSEY |
| Final | 3/5/2025 | OK to Issue CofO | KRISTEN CAUSEY |
| Service/Power Release | 3/5/2025 | Approved | KRISTEN CAUSEY |