753-753 3/4 E ADAMS BLVD 90011
Certificate Information: 753-753 3/4 E ADAMS BLVD 90011
- Application / Permit
- 24016-20000-27927
- Plan Check / Job No.
- B24VN15102
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: CONVERT (E) ATTACHED GARAGE IN DUPLEX TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 10/15/2024
- Issuing Office
- Current Status
- CofO Issued on 8/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | DANIEL YIP |
| Corrections Issued | 9/14/2024 | DANIEL YIP |
| Quality Review Completed | 9/19/2024 | GARO TELMI |
| Plan Check Approved | 10/3/2024 | DANIEL YIP |
| Issued | 10/15/2024 | APPLICANT |
| CofO in Progress | 8/7/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
| CofO Issued | 8/9/2025 | DEROLD HAUFF |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 9/23/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/14/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/6/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/6/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |