19953 W RINALDI ST 91326

Certificate Information: 19953 W RINALDI ST 91326

Application / Permit
24016-20000-27506
Plan Check / Job No.
B24VN14666
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
EPLAN: TENANT IMPROVEMENT TO EXISTING RESTAURANT
Permit Issued
Issued on 12/9/2024
Issuing Office
Current Status
Permit Finaled on 7/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2024 APPLICANT
Assigned to Plan Check Engineer 8/30/2024 PINANK PATEL
Corrections Issued 8/31/2024 PINANK PATEL
Applicant returned to address corrections 11/19/2024 SERGIO MUNIZ
Applicant returned to address corrections 12/3/2024 KAVIAN REFAHI
Plan Check Approved 12/7/2024 MOHAMMAD ESMAILI
Issued 12/9/2024 APPLICANT
Permit Finaled-Status Void 6/11/2025 DEANDRE HOFFMAN
Re-Activate Permit 6/20/2025 DEANDRE HOFFMAN
Permit Finaled-Status Void 7/1/2025 GREGORY POMISH
Re-Activate Permit 7/2/2025 GREGORY POMISH
Permit Finaled 7/17/2025 RICKEY JACKSON

Permit Application Clearance Information

CPC Cleared 10/9/2024 EDWIN CANO
ZA Case Cleared 10/9/2024 EDWIN CANO
Sewer availability Cleared 10/16/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/17/2024 CARLOS AGUILERA
Miscellaneous Cleared 11/7/2024 DORIAN AGUILAR
"D" conditions Cleared 11/15/2024 DORIAN AGUILAR
Specific Plan Cleared 11/15/2024 DORIAN AGUILAR
ZI Cleared 11/15/2024 DORIAN AGUILAR
ZI Cleared 11/15/2024 DORIAN AGUILAR
Food establishment approval Cleared 12/7/2024 LACDHS APPROVED

Contact Information

Architect Gentile,, Ralph Schubart; Lic. No.: NA23538       ,
Contractor Bkb Enterprises Inc; Lic. No.: 1091258-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/7/2025 Approved DEANDRE HOFFMAN
Wood Frame 2/20/2025 Partial Approval DEANDRE HOFFMAN
Light Gage Steel Frame 2/26/2025 Partial Inspection BRIAN KELLY
Insulation 2/28/2025 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/6/2025 Partial Approval DEANDRE HOFFMAN
Special/Order Compliance 3/6/2025 Corrections Issued DEANDRE HOFFMAN
Drywall Nailing 3/21/2025 Approved DEANDRE HOFFMAN
T-Bar Ceiling 5/6/2025 Approved DEANDRE HOFFMAN
Pre-Inspection 5/8/2025 Partial Inspection DEANDRE HOFFMAN
Partition/T-Bar Ceiling 5/15/2025 No Access for Inspection DEANDRE HOFFMAN
T-Bar Ceiling 5/19/2025 Approved DEANDRE HOFFMAN
Final 6/9/2025 Partial Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 6/9/2025 Approved DEANDRE HOFFMAN
Final 6/11/2025 Not Ready for Inspection DEANDRE HOFFMAN
Final 7/1/2025 Partial Inspection GREGORY POMISH