20927 W INGOMAR ST 91304
Certificate Information: 20927 W INGOMAR ST 91304
- Application / Permit
- 24016-20000-27108
- Plan Check / Job No.
- B24VN14269
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (e) detached garage to an ADU per GCS 65852.2(e)(1)(A) per WFPP
- Permit Issued
- Issued on 11/8/2024
- Issuing Office
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2024 | REZA HAGHIGHAT |
| Corrections Issued | 9/9/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 10/20/2024 | REZA HAGHIGHAT |
| Issued | 11/8/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | ALEXANDER HANDY |
| Permit Finaled | 10/2/2025 | JOHN JANSON |
| CofO Issued | 10/2/2025 | JOHN JANSON |
| Permit Finaled | 10/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 9/18/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2025 | Partial Inspection | HENRY KIM |
| Deputy Drilled-In Anchors | 3/25/2025 | Conditional Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 3/28/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 3/28/2025 | Partial Approval | ALEXANDER HANDY |
| Sewer | 3/28/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 3/28/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/23/2025 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/23/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 4/23/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 4/23/2025 | Approved | ALEXANDER HANDY |
| Insulation | 4/29/2025 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 4/29/2025 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/7/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 5/7/2025 | Approved | ALEXANDER HANDY |
| Final | 6/26/2025 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 6/26/2025 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 6/26/2025 | Approved | JEFFREY PARD |
| Final | 7/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 7/11/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/28/2025 | Approved | ALEXANDER HANDY |
| Final | 8/28/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 8/28/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 8/28/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 8/28/2025 | Approved | ALEXANDER HANDY |