18644 W SHERMAN WAY 91335

Certificate Information: 18644 W SHERMAN WAY 91335

Application / Permit
24016-20000-26311
Plan Check / Job No.
B24VN13471
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
EXTERIOR REMODEL TO (E) CHURCH: FACADE REMODEL, REPLACE STOREFRONT, (N) FINISHES & ADD (N) CANOPY (46'-8" X 4') **ePlan**
Permit Issued
Issued on 5/20/2025
Issuing Office
Current Status
Permit Finaled on 5/20/2026

Permit Application Status History

Submitted 8/17/2024 APPLICANT
Assigned to Zoning Architect 8/22/2024 MELISSA QUINONES
Assigned to Plan Check Engineer 9/5/2024 NILOOFAR MEHRAIN
Corrections Issued 9/9/2024 NILOOFAR MEHRAIN
Quality Review Completed 9/13/2024 JASON HEALEY
Applicant returned to address corrections 10/21/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/13/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/18/2024 NILOOFAR MEHRAIN
Plan Check Approved 4/21/2025 NILOOFAR MEHRAIN
Issued 5/20/2025 APPLICANT
Permit Finaled 5/19/2026 BRIAN KELLY

Permit Application Clearance Information

DAS Clearance Cleared 9/10/2024 Angelica Martinez
Green Code Cleared 12/13/2024 MICHAEL AYERS
CPC Cleared 2/11/2025 ASHLEY RODARTE
Miscellaneous Cleared 2/11/2025 ASHLEY RODARTE
ZA Case Cleared 2/13/2025 ASHLEY RODARTE
ZI Cleared 2/18/2025 ASHLEY RODARTE
"Q" conditions Cleared 3/18/2025 ASHLEY RODARTE
Supp. Use District POD/CDO/TDO Cleared 4/3/2025 COURTNEY YELLEN
ZI Cleared 4/3/2025 COURTNEY YELLEN
Zoning Plan Check Cleared 4/8/2025 Angelica Martinez

Contact Information

Architect Jacobson,, Terry Douglas; Lic. No.: C8352 1390 MAIL POUCH LANE      SAN LUIS OBISPO, CA 93405
Contractor Owner-Builder       ,
Engineer Yoo,, Dong Yun; Lic. No.: C85632 8707 WALKER ST APT 10      CYPRESS, CA 90630

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 10/10/2025 Partial Inspection BRIAN KELLY
Wood Frame 10/10/2025 Not Ready for Inspection BRIAN KELLY
Pre-Inspection 10/16/2025 Corrections Issued BRIAN KELLY
Deputy Steel/Welding 12/3/2025 Conditional Approval BRIAN KELLY
Deputy Drilled-In Anchors 1/14/2026 Conditional Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 1/14/2026 Partial Approval BRIAN KELLY
Structural Steel Frame 1/28/2026 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 2/4/2026 Partial Approval BRIAN KELLY
Masonry Wall/Backfill 2/10/2026 Approved BRIAN KELLY
Excavation/Setback/Form/Re-Bar 2/26/2026 Partial Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 3/4/2026 Approved BRIAN KELLY
Wood Frame 3/16/2026 Approved BRIAN KELLY
Final 5/19/2026 Permit Finaled BRIAN KELLY
Green Building Final 5/19/2026 Approved BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Approved BRIAN KELLY
Smoke Detectors 5/19/2026 Approved BRIAN KELLY