22133 W BURBANK BLVD 91367

Certificate Information: 22133 W BURBANK BLVD 91367

Application / Permit
24016-20000-26194
Plan Check / Job No.
B24VN13373
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
STRUCTURAL FRAMING REPAIR DUE TO FIRE DAMAGE OF THE ROOF ONLY , ALL WORK PER ENGINEERING ; "COMPLY WITH DEPARTMENT ORDER effective date 02/06/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 9/25/2024
Issuing Office
Current Status
Permit Finaled on 1/30/2026

Permit Application Status History

Submitted 8/15/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 RARES BODEA
Corrections Issued 8/27/2024 RARES BODEA
Quality Review Completed 8/29/2024 STEVEN KIM
Building Plans Picked Up 8/30/2024 APPLICANT
Green Plans Picked Up 8/30/2024 APPLICANT
Applicant returned to address corrections 9/10/2024 RARES BODEA
Plan Check Approved 9/25/2024 RARES BODEA
Issued 9/25/2024 APPLICANT
Permit Finaled 1/27/2026 BEHROUZ HASHEMI

Permit Application Clearance Information

Green Code Cleared 9/18/2024 MICHAEL AYERS

Contact Information

Contractor Rmk Builders Corp; Lic. No.: 1084377-B 18723 VIA PRINCESSA UNIT 118      CANYON COUNTRY, CA 91387
Engineer Ficinski,, Marek; Lic. No.: S3534 4850 N LANTE ST      BALDWIN PARK, CA 91706

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Corrections Issued DEANDRE HOFFMAN
Order to Comply 10/8/2024 Not Required DEANDRE HOFFMAN
Pre-Inspection 10/8/2024 Partial Inspection DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Approval DEANDRE HOFFMAN
Wood Frame 3/4/2025 Not Ready for Inspection BEHROUZ HASHEMI
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Approved BEHROUZ HASHEMI
Wood Frame 3/18/2025 Approved BEHROUZ HASHEMI
Insulation 4/2/2025 Approved BEHROUZ HASHEMI
Drywall Nailing 4/15/2025 Approved JASON SUMMERS
Final 8/29/2025 Partial Approval BEHROUZ HASHEMI
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved BEHROUZ HASHEMI
Smoke Detectors 8/29/2025 Partial Approval BEHROUZ HASHEMI
Final 9/30/2025 Not Ready for Inspection BEHROUZ HASHEMI
Smoke Detectors 9/30/2025 Not Ready for Inspection BEHROUZ HASHEMI
Final 1/27/2026 Permit Finaled BEHROUZ HASHEMI
Smoke Detectors 1/27/2026 Approved BEHROUZ HASHEMI