7639-7641 N TUJUNGA AVE 91605

Certificate Information: 7639-7641 N TUJUNGA AVE 91605

Application / Permit
24016-20000-26040
Plan Check / Job No.
B24VN13235
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 9/5/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2024 APPLICANT
Assigned to Plan Check Engineer 8/21/2024 JESSE ARELLANO
Corrections Issued 8/22/2024 JESSE ARELLANO
Building Plans Picked Up 8/29/2024 APPLICANT
Applicant returned to address corrections 9/3/2024 KAMYAR EMAMI
Plan Check Approved 9/5/2024 ALEC MOUSAKHANIAN
Issued 9/5/2024 APPLICANT
CofO in Progress 4/4/2025 MATTHEW NELSON
CofO in Progress 4/4/2025 MATTHEW NELSON
CofO in Progress 4/15/2025 MATTHEW NELSON
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/4/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/4/2024 RYAN CASTRO
Sewer availability Cleared 9/4/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/9/2024 Corrections Issued MATTHEW NELSON
Pre-Inspection 9/9/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 9/12/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 9/19/2024 Approved MATTHEW NELSON
Pre-Inspection 9/30/2024 Partial Inspection MATTHEW NELSON
PLUMBING-Rough 10/15/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/23/2024 Partial Approval MATTHEW NELSON
FLOOD-Proofing Certificate 10/23/2024 Corrections Issued MATTHEW NELSON
Final 10/23/2024 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 10/23/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/31/2024 Partial Approval MATTHEW NELSON
FLOOD-Proofing Certificate 12/31/2024 No Access for Inspection MATTHEW NELSON
Final 12/31/2024 No Access for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 12/31/2024 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 1/13/2025 Partial Approval MATTHEW NELSON
FLOOD-Proofing Certificate 1/13/2025 Not Ready for Inspection MATTHEW NELSON
Final 1/13/2025 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/30/2025 Partial Approval MATTHEW NELSON
FLOOD-Proofing Certificate 1/30/2025 Corrections Issued MATTHEW NELSON
HVAC-Rough 1/30/2025 Corrections Issued MATTHEW NELSON
Pre-Inspection 2/3/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 4/3/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 4/3/2025 Approved MATTHEW NELSON
FLOOD-Proofing Certificate 4/3/2025 Approved MATTHEW NELSON
Final 4/3/2025 OK to Issue CofO MATTHEW NELSON