14625 W HUSTON ST 91403

Certificate Information: 14625 W HUSTON ST 91403

Application / Permit
24016-20000-25942
Plan Check / Job No.
B24VN13125
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 1-STORY (20' X 20') GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 11/6/2024
Issuing Office
Current Status
Issued on 11/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/14/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 VAHAN JIVALAGIAN
Corrections Issued 8/23/2024 VAHAN JIVALAGIAN
Quality Review Completed 9/6/2024 OMID HEDAYAT
Building Plans Picked Up 9/11/2024 APPLICANT
Applicant returned to address corrections 9/25/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/6/2024 VAHAN JIVALAGIAN
Issued 11/6/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 9/6/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/9/2024 TAL SHEMEN
Address approval Cleared 9/26/2024 TAL SHEMEN
Construction within easement Cleared 10/2/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2025 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 2/26/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 3/27/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 4/1/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 8/4/2025 Corrections Issued LOUIS ESCOTO
Underground Mechanical 8/4/2025 Corrections Issued LOUIS ESCOTO
BUILDING-Rough-Frame 8/20/2025 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 8/20/2025 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Approved JAVIER RAMOS JR
Green Building Rough 8/20/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 8/20/2025 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Rough 8/20/2025 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 8/20/2025 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 9/23/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 9/23/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Approved WILLIAM WREN
Green Building Rough 9/23/2025 Approved WILLIAM WREN
HVAC-Rough 9/23/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 9/23/2025 Partial Approval WILLIAM WREN
MERV13>=Rough 9/23/2025 Approved WILLIAM WREN
PLUMBING-Rough 9/23/2025 Approved WILLIAM WREN
Insulation 10/8/2025 Approved JACK KARGODORIAN
Drywall Nailing 10/20/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/20/2025 Approved JACK KARGODORIAN
Shower Pan 11/20/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 3/25/2026 Not Ready for Inspection MICHAEL CORTEZ
ELECTRICAL-Final 4/2/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/2/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/27/2026 Approved MICHAEL CORTEZ
PLUMBING-Final 5/22/2026 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved DAVID ANDERSON