9329-9331 N ROSLYNDALE AVE 91331
Certificate Information: 9329-9331 N ROSLYNDALE AVE 91331
- Application / Permit
- 24016-20000-25330
- Plan Check / Job No.
- B24VN12494
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: Convert existing attached garage and portion of existing S.F.D. to JADU per Engineer Calc (Junior ADU per State Law, CA Govt. Code 65852.2(e)(1)(A) and 65852.22)
- Permit Issued
- Issued on 9/25/2024
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | AUNG SOE |
| Corrections Issued | 8/19/2024 | AUNG SOE |
| Applicant returned to address corrections | 9/19/2024 | AUNG SOE |
| Plan Check Approved | 9/19/2024 | AUNG SOE |
| Issued | 9/25/2024 | APPLICANT |
| CofO in Progress | 9/26/2025 | VINCENT HANLEY |
| CofO Issued | 10/16/2025 | RUBEN SALAS |
| Permit Finaled | 10/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 9/6/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evans,, Margarita; Lic. No.: S7278 | 7020 LANEWOOD AVE 204 LOS ANGELES, CA 90028 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/6/2025 | Approved | VINCENT HANLEY |
| Pre-Inspection | 3/6/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/30/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/30/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 4/30/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/30/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | VINCENT HANLEY |
| Insulation | 5/6/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/6/2025 | Approved | VINCENT HANLEY |
| Wood Frame | 5/6/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/10/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/2/2025 | Approved | VINCENT HANLEY |
| Final | 9/4/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 9/4/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/4/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/4/2025 | Approved | VINCENT HANLEY |
| Final | 9/25/2025 | OK to Issue CofO | VINCENT HANLEY |