12536 W KLING ST 91604

Certificate Information: 12536 W KLING ST 91604

Application / Permit
24016-20000-25242
Plan Check / Job No.
B24VN12411
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED STORAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) "COMPLY WITH DEPARTMENT ORDER effective date 07/08/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 12/20/2024
Issuing Office
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 KAMYAR EMAMI
Corrections Issued 8/16/2024 KAMYAR EMAMI
Building Plans Picked Up 8/27/2024 APPLICANT
Plan Check Approved 12/19/2024 DANIEL ABRAMYAN
Issued 12/20/2024 APPLICANT
CofO in Progress 1/15/2025 PTOLEMY HILL
Permit Finaled 4/14/2025 DANIEL SANCHEZ
CofO Issued 4/14/2025 DANIEL SANCHEZ
Permit Finaled 4/14/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 9/7/2024 JOHN LIN
Sewer availability Cleared 9/7/2024 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 9/9/2024 JOHN LIN
Construction near power lines Cleared 12/18/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/24/2024 Approved PTOLEMY HILL
BUILDING-Rough-Frame 1/6/2025 Approved PTOLEMY HILL
ELECTRICAL-Rough 1/6/2025 Approved PTOLEMY HILL
Green Building Rough 1/6/2025 Approved PTOLEMY HILL
HVAC-Rough 1/6/2025 Approved PTOLEMY HILL
MERV13>=Rough 1/6/2025 Approved PTOLEMY HILL
PLUMBING-Rough 1/6/2025 Approved PTOLEMY HILL
ELECTRICAL-Final 1/14/2025 Approved PTOLEMY HILL
Final 1/14/2025 OK to Issue CofO PTOLEMY HILL
Green Building Final 1/14/2025 Approved PTOLEMY HILL
HVAC-Final 1/14/2025 Approved PTOLEMY HILL
MERV13>=Final 1/14/2025 Approved PTOLEMY HILL
PLUMBING-Final 1/14/2025 Approved PTOLEMY HILL
SGSOV-Seismic Gas S/O Valve 1/14/2025 SGSOV Approved PTOLEMY HILL
Smoke Detectors 1/14/2025 Approved PTOLEMY HILL