8421 S WINSFORD AVE 90045
Certificate Information: 8421 S WINSFORD AVE 90045
- Application / Permit
- 24016-20000-25213
- Plan Check / Job No.
- B24VN12383
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE (E) KITCHEN INCLUDING REMOVAL OF LOAD BEARING WALL. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/7/2025
Permit Application Status History
| Submitted | 8/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2024 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 8/7/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 8/16/2024 | APPLICANT |
| Permit Finaled | 4/4/2025 | JESUS PINEDA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/14/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Sb Construction & Remodeling Inc; Lic. No.: 1061509-B | 6513 HOLLYWOOD BLVD #216 LOS ANGELES, CA 90028 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/25/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/26/2024 | Approved | JESUS RODRIGUEZ |
| Rough-Elec/Plmb/HVAC | 10/4/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 10/10/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/10/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/17/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 10/18/2024 | Conditional Approval | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | BOBBY KEY |
| Pre-Inspection | 2/14/2025 | Partial Inspection | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Smoke Detectors | 2/14/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Not Ready | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 3/13/2025 | Corrections Issued | HERBERT GIRON |
| Final | 3/13/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 3/13/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 3/13/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 3/13/2025 | Approved | HERBERT GIRON |
| Special/Order Compliance | 3/13/2025 | Conditional Approval | JESUS PINEDA |
| Final | 4/2/2025 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 4/2/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 4/2/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | JESUS PINEDA |
| Final | 4/4/2025 | Permit Finaled | JESUS PINEDA |