- REMODEL (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 9/13/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/3/2025
Permit Application Status History
| Submitted | 8/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 8/17/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 8/21/2024 | APPLICANT |
| Plan Check Approved | 9/13/2024 | GURUNATH NESARAJAH |
| Issued | 9/13/2024 | APPLICANT |
| Permit Finaled | 9/2/2025 | ALEXANDER HANDY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/13/2024 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/16/2024 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/21/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 10/21/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/4/2024 | Partial Approval | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 12/4/2024 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 12/9/2024 | Conditional Approval | ALEXANDER HANDY |
| Insulation | 12/10/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/10/2024 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 12/20/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/20/2024 | Approved | ALEXANDER HANDY |
| Gas Test | 3/24/2025 | Approved | ALEXANDER HANDY |
| Pool Piping | 3/24/2025 | Partial Inspection | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 3/25/2025 | Conditional Approval | ALEXANDER HANDY |
| Deputy Wood Construction | 3/28/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/4/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Underground Mechanical | 4/4/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Final | 7/1/2025 | Corrections Issued | HENRY KIM |
| Final | 7/1/2025 | Corrections Issued | HENRY KIM |
| HVAC-Final | 7/1/2025 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 7/1/2025 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 7/1/2025 | Approved | HENRY KIM |
| Final | 9/2/2025 | Permit Finaled | ALEXANDER HANDY |