1209 1/2 S HIGHLAND AVE 90019
Certificate Information: 1209 1/2 S HIGHLAND AVE 90019
- Application / Permit
- 24016-20000-25196
- Plan Check / Job No.
- B24VN12367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18'-8" X 20' PORTION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (ONE CAR GARAGE TO REMAIN). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 8/19/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 8/20/2024 | APPLICANT |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 9/12/2025 | JUSTIN HAWLEY |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2024 | WALLIE JONG |
| Sewer availability | Cleared | 8/27/2024 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 8/29/2024 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2024 | WALLIE JONG |
| ZI | Cleared | 11/1/2024 | NATHAN ROMINE |
| Construction near power lines | Cleared | 12/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Elite Home Builders; Lic. No.: 1070934-B | 10866 WASHINGTON BLVD 843 CULVER CITY, CA 90232 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/18/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/24/2025 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 2/24/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/18/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 3/18/2025 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/23/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Corrections Issued | JOSE MACIAS |
| Gas Test | 4/23/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 4/23/2025 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 4/23/2025 | Corrections Issued | JOSE MACIAS |
| Sewer | 4/23/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 4/23/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/14/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/19/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 5/19/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Rough | 5/19/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/19/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 5/19/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 5/30/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 5/30/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 5/30/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 6/4/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/4/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/10/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 6/10/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 6/10/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/10/2025 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/17/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 9/4/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/4/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 9/4/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 9/4/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 9/4/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 9/4/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/12/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| Service/Power Release | 9/12/2025 | Approved | JUSTIN HAWLEY |