16625 W TULSA ST 91344
Certificate Information: 16625 W TULSA ST 91344
- Application / Permit
- 24016-20000-25139
- Plan Check / Job No.
- B24VN12323
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan - Convert existing 374 SF detached garage into ADU per WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- Current Status
- CofO Issued on 3/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | AUNG SOE |
| Corrections Issued | 8/20/2024 | AUNG SOE |
| Plan Check Approved | 8/28/2024 | AUNG SOE |
| Issued | 10/4/2024 | APPLICANT |
| CofO in Progress | 2/11/2025 | JAVIER RAMOS JR |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
| CofO Issued | 3/15/2025 | RUBEN SALAS |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 8/21/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2024 | RYAN CASTRO |
Contact Information
| Contractor | Acm General Construction Inc; Lic. No.: 1056326-B | 11289 HERRICK AVE PACOIMA, CA 91331 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/23/2024 | Partial Approval | DAVID ANDERSON |
| Sewer | 10/23/2024 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/29/2024 | Not Ready for Inspection | ROBERT GOLD |
| Sewer | 10/29/2024 | Approved | ROBERT GOLD |
| Underground Mechanical | 10/29/2024 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 10/31/2024 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 10/31/2024 | Approved | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 11/4/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/6/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/20/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/20/2024 | Corrections Issued | JAVIER RAMOS JR |
| Wood Frame | 11/20/2024 | Partial Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/2/2024 | Partial Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/2/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 12/2/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/6/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/6/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 12/6/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/6/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/12/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/12/2024 | Approved | LOUIS ESCOTO |
| Final | 1/16/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/16/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/23/2025 | Approved | JAVIER RAMOS JR |
| Final | 1/23/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 1/23/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/23/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/23/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 2/7/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/11/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 2/11/2025 | Approved | JAVIER RAMOS JR |