16625 W TULSA ST 91344

Certificate Information: 16625 W TULSA ST 91344

Application / Permit
24016-20000-25139
Plan Check / Job No.
B24VN12323
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan - Convert existing 374 SF detached garage into ADU per WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 10/4/2024
Issuing Office
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/16/2024 AUNG SOE
Corrections Issued 8/20/2024 AUNG SOE
Plan Check Approved 8/28/2024 AUNG SOE
Issued 10/4/2024 APPLICANT
CofO in Progress 2/11/2025 JAVIER RAMOS JR
Permit Finaled 3/15/2025 RUBEN SALAS
CofO Issued 3/15/2025 RUBEN SALAS
Permit Finaled 3/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/21/2024 RYAN CASTRO
Sewer availability Cleared 8/21/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/23/2024 RYAN CASTRO

Contact Information

Contractor Acm General Construction Inc; Lic. No.: 1056326-B 11289 HERRICK AVE      PACOIMA, CA 91331

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 10/23/2024 Partial Approval DAVID ANDERSON
Sewer 10/23/2024 Approved DAVID ANDERSON
Footing/Foundation/Slab 10/29/2024 Not Ready for Inspection ROBERT GOLD
Sewer 10/29/2024 Approved ROBERT GOLD
Underground Mechanical 10/29/2024 Corrections Issued ROBERT GOLD
PLUMBING-Rough 10/31/2024 Corrections Issued JACK KARGODORIAN
Underground Mechanical 10/31/2024 Approved JACK KARGODORIAN
Deputy Drilled-In Anchors 11/4/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 11/6/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 11/20/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 11/20/2024 Corrections Issued JAVIER RAMOS JR
Wood Frame 11/20/2024 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 12/2/2024 Partial Approval KEVIN BERBERYAN
Interior/Exterior Lathing 12/2/2024 Approved KEVIN BERBERYAN
Shower Pan 12/2/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/6/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 12/6/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Approved JAVIER RAMOS JR
HVAC-Rough 12/6/2024 Approved JAVIER RAMOS JR
Insulation 12/6/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/6/2024 Approved JAVIER RAMOS JR
Drywall Nailing 12/12/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 12/12/2024 Approved LOUIS ESCOTO
Final 1/16/2025 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 1/16/2025 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 1/23/2025 Approved JAVIER RAMOS JR
Final 1/23/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 1/23/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 1/23/2025 Approved JAVIER RAMOS JR
Smoke Detectors 1/23/2025 Approved JAVIER RAMOS JR
Green Building Final 2/7/2025 Approved JAVIER RAMOS JR
Final 2/11/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 2/11/2025 Approved JAVIER RAMOS JR