597 W AVENUE 46 90065

Certificate Information: 597 W AVENUE 46 90065

Application / Permit
24016-20000-25070
Plan Check / Job No.
B24VN12253
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 13'11"' X 7'11" ADDITION OF REAR DECK WITH PATIO COVER ABOVE AND NEW 9'11" X 32' DECK AT 2ND FLOOR , ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/23/2025
Issuing Office
Valley
Current Status
Issued on 1/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 RARES BODEA
Corrections Issued 8/13/2024 RARES BODEA
Quality Review Completed 8/15/2024 STEVEN KIM
Building Plans Picked Up 8/16/2024 APPLICANT
Applicant returned to address corrections 12/19/2024 RARES BODEA
Plan Check Approved 1/8/2025 RARES BODEA
Issued 1/23/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/3/2024 TREVOR QUAN
Specific Plan Cleared 12/17/2024 ANDREA MAGANA-WITHERS
ZI Cleared 12/17/2024 ANDREA MAGANA-WITHERS
Roof/Waste drainage to street Cleared 12/19/2024 CHRISTINA BRACO
Miscellaneous Cleared 1/6/2025 DORIAN AGUILAR
ZI Cleared 1/6/2025 DORIAN AGUILAR
Grading Pre-Inspection Cleared 1/8/2025 RARES BODEA

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor Brown Richard Keith; Lic. No.: 628681-B 10652 DARLING RD      AGUA DULCE, CA 91390
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/30/2025 Conditional Approval ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 5/7/2025 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/14/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/16/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/20/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/31/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 9/4/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 1/20/2026 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/28/2026 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/28/2026 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/29/2026 Partial Approval ALIZAH MAYAGOITIA
Insulation 2/23/2026 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/4/2026 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/4/2026 Approved ALIZAH MAYAGOITIA
Drywall Nailing 4/20/2026 Approved ALIZAH MAYAGOITIA