3513 W MONT CLAIR ST 90018

Certificate Information: 3513 W MONT CLAIR ST 90018

Application / Permit
24016-20000-24828
Plan Check / Job No.
B24VN11989
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert 20' x 18'-6" portion of existing detached garage to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 02/01/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/6/2024 ANGELICA DAVE
Corrections Issued 8/6/2024 ANGELICA DAVE
Building Plans Picked Up 8/9/2024 APPLICANT
Plan Check Approved 11/6/2024 ANGELICA MARTINEZ
Issued 11/6/2024 APPLICANT
CofO in Progress 6/6/2025 WILLIAM MICHALAK
Permit Finaled 3/23/2026 CLAUDIO MORENO
Permit Finaled 3/23/2026 CLAUDIO MORENO
CofO Issued 3/23/2026 CLAUDIO MORENO

Permit Application Clearance Information

Miscellaneous Cleared 8/12/2024 NATHAN ROMINE
Miscellaneous Cleared 8/12/2024 NATHAN ROMINE
Address approval Cleared 8/15/2024 JUSTIN BICOL
Sewer availability Cleared 8/15/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 8/21/2024 JUSTIN BICOL
HPOZ Cleared 10/31/2024 DANIEL MATA

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B 13302 FILMORE ST      PACOIMA, CA 91331

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/20/2024 Approved WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 12/17/2024 Approved WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Approved WILLIAM MICHALAK
HVAC-Rough 12/17/2024 Corrections Issued WILLIAM MICHALAK
PLUMBING-Rough 12/17/2024 Approved WILLIAM MICHALAK
Wood Frame 12/17/2024 Approved WILLIAM MICHALAK
Insulation 1/6/2025 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 1/6/2025 Approved WILLIAM MICHALAK
Drywall Nailing 1/14/2025 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 1/14/2025 Partial Approval WILLIAM MICHALAK
Underground Mechanical 1/31/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 2/28/2025 Approved WILLIAM MICHALAK
Final 2/28/2025 No Access for Inspection WILLIAM MICHALAK
Green Building Final 2/28/2025 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 2/28/2025 Approved WILLIAM MICHALAK
METHANE-Final 2/28/2025 Approved WILLIAM MICHALAK
METHANE-Rough 2/28/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 2/28/2025 Approved WILLIAM MICHALAK
ELECTRICAL-Final 3/4/2025 Approved WILLIAM MICHALAK
HVAC-Final 3/4/2025 Approved WILLIAM MICHALAK
PLUMBING-Final 3/4/2025 Approved WILLIAM MICHALAK
Final 4/9/2025 Corrections Issued WILLIAM MICHALAK
Green Building Final 4/9/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Not Ready WILLIAM MICHALAK
Final 6/6/2025 OK to Issue CofO WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Approved WILLIAM MICHALAK