22505-22507 W MACFARLANE DR 91364
Certificate Information: 22505-22507 W MACFARLANE DR 91364
- Application / Permit
- 24016-20000-24781
- Plan Check / Job No.
- B24VN11956
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF SFD 396 SF TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22.
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 8/10/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/13/2024 | APPLICANT |
| Applicant returned to address corrections | 9/27/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 1/16/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 1/16/2025 | YAQUB MIRZA |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 4/30/2025 | KIM BEAUCHAMP |
| Permit Finaled | 6/5/2025 | DAVID JAMES |
| CofO Issued | 6/5/2025 | DAVID JAMES |
| Permit Finaled | 6/5/2025 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/18/2025 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/18/2025 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/18/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/24/2025 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/24/2025 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/24/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/12/2025 | Not Ready for Inspection | KIM BEAUCHAMP |
| Final | 3/12/2025 | Not Ready for Inspection | KIM BEAUCHAMP |
| Pre-Inspection | 3/12/2025 | Corrections Issued | KIM BEAUCHAMP |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Not Ready | KIM BEAUCHAMP |
| Smoke Detectors | 3/12/2025 | Corrections Issued | KIM BEAUCHAMP |
| Insulation | 4/16/2025 | Approved | KIM BEAUCHAMP |
| Rough-Elec/Plmb/HVAC | 4/16/2025 | Corrections Issued | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | KIM BEAUCHAMP |
| Final | 4/22/2025 | OK to Issue CofO | KIM BEAUCHAMP |
| Rough-Elec/Plmb/HVAC | 4/22/2025 | Approved | KIM BEAUCHAMP |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | KIM BEAUCHAMP |
| Smoke Detectors | 4/22/2025 | Approved | KIM BEAUCHAMP |