1109 S BUNDY DR 90049

Certificate Information: 1109 S BUNDY DR 90049

Application / Permit
24016-20000-24639
Plan Check / Job No.
B24VN11769
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ACCESSORY LIVING QUARTERS TO ACCESSORY DWELLING UNIT (1397 SQ FT) PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/30/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 JEROME MAGAT PALMA
Corrections Issued 8/8/2024 JEROME MAGAT PALMA
Building Plans Picked Up 8/9/2024 APPLICANT
Plan Check Approved 10/30/2024 SARKIS HARABEDIAN
Issued 10/30/2024 APPLICANT
CofO in Progress 1/10/2025 KIRK SANDERS
Permit Finaled 1/14/2025 RICHARD STEINBACH
CofO Issued 1/14/2025 RICHARD STEINBACH
Permit Finaled 1/14/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/16/2024 ANTHONY MAINEZ
Sewer availability Cleared 9/16/2024 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 9/17/2024 ANTHONY MAINEZ
Specific Plan Cleared 10/28/2024 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/8/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 12/20/2024 Approved KIRK SANDERS
Final 12/20/2024 Corrections Issued KIRK SANDERS
HVAC-Final 12/20/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 12/20/2024 Approved KIRK SANDERS
PLUMBING-Final 12/20/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 12/20/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 1/3/2025 Approved KIRK SANDERS
ELECTRICAL-Final 1/3/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 1/3/2025 Approved KIRK SANDERS
Final 1/3/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 1/3/2025 Approved KIRK SANDERS
HVAC-Rough 1/3/2025 Approved KIRK SANDERS
METHANE-Final 1/3/2025 Approved KIRK SANDERS
METHANE-Rough 1/3/2025 Approved KIRK SANDERS
PLUMBING-Final 1/3/2025 Approved KIRK SANDERS
PLUMBING-Rough 1/3/2025 Approved KIRK SANDERS
Rough-Elec/Plmb/HVAC 1/3/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 1/3/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 1/3/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 1/10/2025 Approved KIRK SANDERS
Final 1/10/2025 OK to Issue CofO KIRK SANDERS
HVAC-Final 1/10/2025 Approved KIRK SANDERS
PLUMBING-Final 1/10/2025 Approved KIRK SANDERS
Smoke Detectors 1/10/2025 Approved KIRK SANDERS