14513 W ASTORIA ST 91342

Certificate Information: 14513 W ASTORIA ST 91342

Application / Permit
24016-20000-24475
Plan Check / Job No.
B24VN11595
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) DETACHED 2 CAR GARAGE INTO AN ADU. per Ordinance
Permit Issued
Issued on 9/6/2024
Issuing Office
Current Status
CofO Issued on 4/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2024 APPLICANT
Assigned to Plan Check Engineer 8/6/2024 JOSE VELAZQUEZ
Corrections Issued 8/7/2024 JOSE VELAZQUEZ
Plan Check Approved 9/5/2024 LUKE GONZALES
Issued 9/6/2024 APPLICANT
CofO in Progress 3/26/2025 KEVIN BERBERYAN
Permit Finaled 4/8/2025 RUBEN SALAS
CofO Issued 4/8/2025 RUBEN SALAS
Permit Finaled 4/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/14/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/14/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/15/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/10/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 10/1/2024 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 10/1/2024 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 10/1/2024 Approved KEVIN BERBERYAN
HVAC-Rough 10/1/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 10/1/2024 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 10/10/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 10/10/2024 Approved KEVIN BERBERYAN
HVAC-Rough 10/10/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 10/10/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/17/2024 Approved KEVIN BERBERYAN
Shower Pan 10/17/2024 Approved KEVIN BERBERYAN
Insulation 10/21/2024 Conditional Approval KEVIN BERBERYAN
Interior/Exterior Lathing 10/21/2024 Approved KEVIN BERBERYAN
Drywall Nailing 10/29/2024 Approved KEVIN BERBERYAN
Final 3/4/2025 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/4/2025 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 3/4/2025 Approved KEVIN BERBERYAN
Final 3/21/2025 OK to Issue CofO KEVIN BERBERYAN