18218 W VANOWEN ST 91335

Certificate Information: 18218 W VANOWEN ST 91335

Application / Permit
24016-20000-24405
Plan Check / Job No.
B24VN11490
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 6/3/2025
Issuing Office
Valley
Current Status
CofO Corrected on 2/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2024 APPLICANT
Assigned to Plan Check Engineer 8/7/2024 OMAR GARNICA
Corrections Issued 8/7/2024 OMAR GARNICA
Building Plans Picked Up 8/13/2024 APPLICANT
Applicant returned to address corrections 2/7/2025 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 5/15/2025 GURUNATH NESARAJAH
Issued 6/3/2025 APPLICANT
CofO in Progress 2/26/2026 JUAN ALVARADO
CofO Issued-Status Void 2/26/2026 JOHN JANSON
Permit Finaled-Status Void 2/26/2026 JOHN JANSON
Re-Activate Permit 2/27/2026 JOHN JANSON
Permit Finaled 2/27/2026 JOHN JANSON
CofO Corrected 2/27/2026 JOHN JANSON
Permit Finaled 2/27/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/28/2024 RYAN CASTRO
Sewer availability Cleared 8/28/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/30/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/20/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/25/2025 Corrections Issued ROBERT GOLD
Sewer 6/25/2025 Corrections Issued ROBERT GOLD
Footing/Foundation/Slab 6/30/2025 Approved JUAN ALVARADO
PLUMBING-Rough 6/30/2025 Partial Approval JUAN ALVARADO
Gas Test 7/7/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 7/7/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 7/15/2025 Approved JUAN ALVARADO
Sewer 7/15/2025 Approved JUAN ALVARADO
Wood Frame 7/15/2025 Partial Approval JUAN ALVARADO
BUILDING-Rough-Frame 7/23/2025 Approved JUAN ALVARADO
ELECTRICAL-Rough 7/23/2025 Approved JUAN ALVARADO
Green Building Rough 7/23/2025 Approved JUAN ALVARADO
HVAC-Rough 7/30/2025 Approved GEVORK IPCHYAN
Insulation 7/30/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 7/30/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 7/30/2025 Approved GEVORK IPCHYAN
Drywall Nailing 8/4/2025 Approved JUAN ALVARADO
Final 9/17/2025 Corrections Issued JUAN ALVARADO
Green Building Final 9/17/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 9/17/2025 Approved JUAN ALVARADO
Underground Mechanical 9/17/2025 Approved JUAN ALVARADO
Final 1/29/2026 Not Ready for Inspection JUAN ALVARADO
Final 2/3/2026 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 2/11/2026 Approved JUAN ALVARADO
Final 2/11/2026 Not Ready for Inspection JUAN ALVARADO
HVAC-Final 2/11/2026 Approved JUAN ALVARADO
PLUMBING-Final 2/11/2026 Approved JUAN ALVARADO
Service/Power Release 2/11/2026 Not Ready for Inspection JUAN ALVARADO
Final 2/25/2026 OK to Issue CofO JUAN ALVARADO