18218 W VANOWEN ST 91335
Certificate Information: 18218 W VANOWEN ST 91335
- Application / Permit
- 24016-20000-24405
- Plan Check / Job No.
- B24VN11490
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/3/2025
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2024 | OMAR GARNICA |
| Corrections Issued | 8/7/2024 | OMAR GARNICA |
| Building Plans Picked Up | 8/13/2024 | APPLICANT |
| Applicant returned to address corrections | 2/7/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 5/15/2025 | GURUNATH NESARAJAH |
| Issued | 6/3/2025 | APPLICANT |
| CofO in Progress | 2/26/2026 | JUAN ALVARADO |
| CofO Issued-Status Void | 2/26/2026 | JOHN JANSON |
| Permit Finaled-Status Void | 2/26/2026 | JOHN JANSON |
| Re-Activate Permit | 2/27/2026 | JOHN JANSON |
| Permit Finaled | 2/27/2026 | JOHN JANSON |
| CofO Corrected | 2/27/2026 | JOHN JANSON |
| Permit Finaled | 2/27/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 8/28/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/25/2025 | Corrections Issued | ROBERT GOLD |
| Sewer | 6/25/2025 | Corrections Issued | ROBERT GOLD |
| Footing/Foundation/Slab | 6/30/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 6/30/2025 | Partial Approval | JUAN ALVARADO |
| Gas Test | 7/7/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 7/7/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 7/15/2025 | Approved | JUAN ALVARADO |
| Sewer | 7/15/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 7/15/2025 | Partial Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 7/23/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 7/23/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 7/23/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 7/30/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 7/30/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 7/30/2025 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 7/30/2025 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 8/4/2025 | Approved | JUAN ALVARADO |
| Final | 9/17/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 9/17/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 9/17/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 9/17/2025 | Approved | JUAN ALVARADO |
| Final | 1/29/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 2/3/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/11/2026 | Approved | JUAN ALVARADO |
| Final | 2/11/2026 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Final | 2/11/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 2/11/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 2/11/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 2/25/2026 | OK to Issue CofO | JUAN ALVARADO |